Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
Permit Number - DP18-0212
Inspection Description - ENGR Engineering Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Engineering Final | Not Ready | ||
08/14/2020 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by JSCHNEI2 - Partially approved. Project is ongoing and not ready for final inspections at this time. |
08/24/2020 | ENGR Engineering Final | DROBERTS | Approved | Entered by DROBERT5 - |
08/14/2020 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by JSCHNEI2 - Partially approved. Project is ongoing and not ready for final inspections at this time. |
12/18/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - It appears that DP 18 Dash 0107 also applies to the same job site. |
09/24/2019 | ENGR Engineering Final | JV | Prior to Final Inspectn | Entered by JVWINKL1 - Prior to final, asbuilt drawings needed. First change is addition of 1 layer of gabion at outlet structures into rodeo wash |