Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Engineering Final
|
|
Not Ready |
|
| 10/27/2022 |
ENGR Engineering Final
|
|
Not Ready |
|
| 02/09/2021 |
ENGR Engineering Final
|
DROBERTS |
Denied |
Entered by VLEON1 - DENIED, PROVIDE APPROVED REVISED DRAWINGS FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITE. |
| 06/15/2020 |
ENGR Engineering Final
|
RLEDONNE |
Continued |
Entered by RSALDAT1 - Continue. Same notes from engineering final. |
| 05/21/2020 |
ENGR Engineering Final
|
RLEDONNE |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. ADA parking over 2% Met with owner on site. |
| 05/19/2020 |
ENGR Engineering Final
|
RLEDONNE |
Partial Approval |
Entered by RSALDAT1 - Partial approval. OK forTCO only. ADA parking and drop off area over 2%. Complete work on development package per approved plansOr provide city approve revisions for all changes. |
| 05/08/2020 |
ENGR Engineering Final
|
DROBERTS |
Not ready for Inspection |
Entered by RSALDAT1 - IS NOT READY AT THIS TIME DUE TO THE ADA PARKING AND ACCESS AISLES ARE NON-COMPLIANT FOR SLOPE, VARIES FROM 2% TO 4%. |
| 02/18/2020 |
ENGR Engineering Final
|
RLEDONNE |
Partial Approval |
Entered by DMERANZ1 - Engineering final notes Same as grading final. |
| 02/11/2020 |
ENGR Engineering Final
|
RLEDONNE |
Not ready for Inspection |
Entered by DMERANZ1 - Provide accessible route from ADA parking to front access. Landing at front door not in compliance.Provide CO T approved revisions for all changes to approved plans. |
| 07/30/2021 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by VLEON1 - not ready. Un-scheduled inspection. Pending plan revision.Per Dave Roberts 2/9/21 |
| 02/09/2021 |
ENGR Engineering Final
|
DROBERTS |
Partial Approval |
Entered by VLEON1 - PARTIAL AT THIS TIME, OK FOR TCO BUT NOT FOR FINAL. SEE THE COMMENT NOTED ABOVE IN THE FINAL GRADING INSPECTION FOR THIS SITE. |
| 06/15/2020 |
ENGR Engineering Final
|
RLEDONNE |
Continued |
Entered by RSALDAT1 - Continue. ADA parking i’m south side of new building percentages on slopes OK. TCO OK for building one per engineering only. Complete all work on development package for finals. |
| 02/18/2020 |
ENGR Engineering Final
|
RLEDONNE |
Partial Approval |
Entered by DMERANZ1 - OK for TCO only. Complete all work on approved plans. Provide city of Tucson approved revisions for all changes to approved plans before final. |
| 11/25/2019 |
ENGR Engineering Final
|
RLEDONNE |
Not ready for Inspection |
Entered by DMERANZ1 - site is being worked on. General contractor not on site |
| 11/06/2023 |
ENGR Engineering Final
|
|
Partial Pass |
sidewalk on southwest side has several trip hazards. ADA parking should include van accessible sign and be restriped (striping barely visible and appears to used non-ADA parking). |
| 11/06/2023 |
ENGR Engineering Final
|
|
Passed |
|