Inspection Status: Passed
Inspection History: PDSD Site/Engineering Division - Landscaping
| Date |
Description |
Inspector |
Results |
Comments |
| 02/11/2020 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Approved |
Entered by DMERANZ1 - Complete ground covering as required |
| 02/10/2020 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Partial Approval |
Entered by DMERANZ1 - Recessed landscape areas as required. Double stake trees |
| 02/20/2020 |
PDSD Site/Engineering Division - Landscaping |
RLEDONNE |
Approved |
Entered by DMERANZ1 - |
| 02/18/2020 |
PDSD Site/Engineering Division - Landscaping |
DROBERTS |
Partial Approval |
Entered by DMERANZ1 - REMOVE ALL NURSERY STAKES AS NEEDED, ALL OTHER LANDSCAPING APPEARS TO BE COMPLETE.
|
| 02/07/2020 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Partial Approval |
Entered by DMERANZ1 - Remove the nursery stakes and support trees as required. |
| 01/16/2020 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - I spoke with Dan the superintendent about the final grading prior to installing landscaping.
|
| 01/14/2020 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - Depress landscaped areas as required prior to installing plants. Contractor is installing irrigation at this time. |