Permit: DP18-0186

Parcel: 121116580


Addresses:

Inspection Status: Not Ready

Inspection History: SITE - Stormwater Setup and Controls

Date Description Inspector Results Comments
10/26/2022 SITE - Stormwater Setup and Controls Not Ready
10/11/2023 SITE - Stormwater Setup and Controls Partial Pass Sam controls have been placed and perimeter block wall has been installed
11/07/2023 SITE - Stormwater Setup and Controls Not Ready gate locked no accesss
12/13/2023 SITE - Stormwater Setup and Controls Complete (Recurring) wattles around soil piles need to be installed, track out onto Bellevue needs improvement, trash west of entrance paralleling Bellevue needs cleaning.