Permit: DP18-0183

Parcel: 11106157A

Inspection Status: Not Ready

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
04/05/2022 ENGR Grading Final BBENEDON Not ready for Inspection Entered by NGARCIA3 - not ready. Dan with Castle construction at 260-2728. Provide documentation as discussed for trash enclosure rebar. Correct all accessible walkways that exceed 2% cross slope
03/17/2021 ENGR Grading Final BBENEDON Denied Entered by RSALDAT1 - Denied. 40% of all common area accessible walkways are out of compliance. Trash enclosure bollards are out of compliance with COT standard detail 601. Enclosure was constructed without inspecti
04/07/2022 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Dan with Castle construction at 260-2728. Claims to be new on the project. Has read the comments online and is aware of the cross slope issues that require correction. Dan also claims to have photo documentation to support installation of trash enclosure for standard detail 601
05/11/2021 ENGR Grading Final BBENEDON Continued Entered by VLEON1 - CONTINUE PROJECT IS ONGOING
07/29/2020 ENGR Grading Final BBENEDON Continued Entered by JSCHNEI2 - Continued. There is ongoing construction including curbs and utility work. There is no address posted. There’s no SWPPP posted there is no job trailer. There’s no contact information listed in Pro. There is track out in the street. There is no track out protection and no efforts being made to control dust, and dirt within the site. Reported work being done at 3 AM by the neighbor across the street. Contractor shall schedule inspections, comply with all regulations and maintain all materials within the site. Provide contact information when scheduling inspections.
11/29/2019 ENGR Grading Final DROBERTS Not ready for Inspection Entered by DMERANZ1 - GRADING WORK HAS STARTED FOR THE ROADWAY AND PAD BUT NOTHING HAS BEEN INSPECTED. THIS SITE DOES NOT HAVE A SWPPP BOARD FOR THE SITE INFORMATION. THERE ARE WADDLES PLACED SOUTH OF MONTE VISTA DR, ADDITIONAL WORK MAY BE REQUIRED.
10/09/2018 ENGR Grading Final bbenedo1 Not ready for Inspection Entered by BBENEDO1 - SITE IS FENCED. THERE IS NO ACTIVITY.
06/29/2022 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - . Continue. No site activity at this time. Temporary fencing in place and locked.
05/11/2022 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. No changes since last inspection.
05/03/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Dan with Castle Construction is addressing Elevation discrepancies which appears to be the cause of the sidewalk slope issues
04/05/2022 ENGR Grading Final BBENEDON Not ready for Inspection Entered by NGARCIA3 - not ready. Dan with Castle construction at 260-2728. Provide documentation as discussed for trash enclosure rebar. Correct all accessible walkways that exceed 2% cross slope
03/17/2021 ENGR Grading Final BBENEDON Denied Entered by RSALDAT1 - Denied. 40% of all common area accessible walkways are out of compliance. Trash enclosure bollards are out of compliance with COT standard detail 601. Enclosure was constructed without inspecti
03/11/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - GRADING INTERMEDIATE AC PAVEMENT, CURBS AND SCUPPERS HAVE BEEN CONSTRUCTED THROUGHOUT THE SITE WITHOUT INSPECTIONS. THIS SITE WILL BE SCHEDULED SO THAT BRIAN CAN CHECK THE SIDEWALKS FOR ADA COMPLIANCY.
08/20/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Forms have been installed for sidewalk within city right of way. Contractor has been informed that he needs to schedule inspections from his City of Tucson department of transportation right of way permit. Dan with Castle construction at 999-1819 also concrete Contractor 850-5505
06/15/2023 ENGR Grading Final Complete (Recurring) no activity on site at this time. Perimeter fencing in place.
10/03/2023 ENGR Grading Final Passed project complete and occupied
10/03/2023 ENGR Grading Final Passed project complete and occupied
10/03/2023 ENGR Grading Final Passed project complete and occupied