05/01/2019 ENGR Grading Final BBENEDON Approved Entered by CBELL1 - Trash enclosure apron.
03/21/2019 ENGR Grading Final BBENEDON Approved Entered by CBELL1 - Trash enclosure is OK for concrete
03/15/2019 ENGR Grading Final BBENEDON Partial Approval Entered by CBELL1 - Trash closure footing is OK for concrete. Half of the site has been paved and curbs have been poured. Note depressed landscaped areas shall be 6 inches below the inlet of the curb openings at final inspection.
07/18/2019 ENGR Grading Final BBENEDON Approved Entered by VFLORES1 -
11/16/2018 ENGR Grading Final bbenedo1 Continued Entered by BBENEDO1 - Contractor not on site, I left a card and inspection form reqesting inspections for storm water. Basin cut along west side of lot. Contractor installing building pad.
07/19/2019 ENGR Grading Final BBENEDON Approved Entered by VFLORES1 -
08/02/2019 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
07/18/2019 ENGR Grading Final BBENEDON Denied Entered by VFLORES1 - Water harvesting plan on page 12, line item number eight, requires 6 inches depth in all water harvesting locations. I spoke with Mike with Chestnut about this three times prior to any landscaping being installed, however the water harvesting areas have only been depressed roughly 1 to 2 inches below bottom of curb openings, and roughly 3 inches below top of curb where there is no curb opening. Mike said that he installed the grading as directed by his engineer.
05/01/2019 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - Contractor is installing curbs.
04/03/2019 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - The site grading appears to be complete. Riprap has been installed along the basin. Superintendent not on site at this time to see the plans.
03/21/2019 ENGR Grading Final BBENEDON Not ready for Inspection Entered by CBELL1 - Mike from Chestnut is not on site however I spoke with him over the telephone and gave him a heads up about the water harvesting and grading requirements. But I have not seen the plan documents
03/15/2019 ENGR Grading Final BBENEDON Partial Approval Entered by CBELL1 - Trash closure footing is OK for concrete. Half of the site has been paved and curbs have been poured. Note depressed landscaped areas shall be 6 inches below the inlet of the curb openings at final inspection.
11/19/2018 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - Contractor installing utilities
11/16/2018 ENGR Grading Final bbenedo1 Continued Entered by BBENEDO1 - Contractor not on site, I left a card and inspection form reqesting inspections for storm water. Basin cut along west side of lot. Contractor installing building pad.