Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Grading Final
Permit Number - DP18-0162
Inspection Description - ENGR Grading Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
05/07/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. Jewish community center parking lot improvements |
04/22/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - CONTINUE JCC PARKING LOT EXPANSION NO HISTORY |
08/28/2023 | ENGR Grading Final | Not Ready | This site was constructed as shown on the Approved Plans. | |
08/28/2023 | ENGR Grading Final | Not Ready | This site was constructed as shown on the Approved Plans. | |
08/28/2023 | ENGR Grading Final | Not Ready | This site was constructed as shown on the Approved Plans. |