Inspection History Details
Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
Permit Number - DP18-0147
Inspection Description - PDSD Engineering Division Pre-Construction SITE
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/24/2019 | PDSD Engineering Division Pre-Construction SITE | BBENEDON | Approved | Entered by DMERANZ1 - |
02/28/2019 | PDSD Engineering Division Pre-Construction SITE | BBENEDON | Not ready for Inspection | Entered by CBELL1 - Contractor has SWPPP paperwork. Post your signage and complete installation of controls. |
02/19/2019 | PDSD Engineering Division Pre-Construction SITE | BBENEDON | Not ready for Inspection | Entered by CBELL1 - I spoke with Dave superintendent, and provided him with city of Tucson preconstruction meeting form. I instructed him to install stormwater controls and to call for preconstruction meeting. He said his Engineer of record has instructed him on where to install stormwater controls. |
02/15/2019 | PDSD Engineering Division Pre-Construction SITE | BBENEDON | Not ready for Inspection | Entered by CBELL1 - Dave Roberts has instructed me to require an Anna lie from the state of Arizona for your swift requirements and that you install stormwater controls as required. Schedule a preconstruction meeting from your DP permit. Fill out the city of Tucson preconstruction meeting form and provide this to the inspecto |
02/14/2019 | PDSD Engineering Division Pre-Construction SITE | BBENEDON | Partial Approval | Entered by CBELL1 - This was an unscheduled inspection for Dave with CTC renovations at 818-3 12-6116. Note this project is well underway, this project is just over 1 acre, but no NOI has been obtained, no stormwater controls have been installed. Provide approved permits. Schedule inspections from DP permits for all work shown on DP plan except for retaining walls. Track out onto all public street shall be cleaned. Provide SWIPP and controls as required and schedule Stormwater inspections by weekly. |