Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP18-0147
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/14/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by CBELL1 - Trash closure mats are OK for concrete. |
02/22/2019 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by CBELL1 - They have not yet started stacking block for the trash enclosures. |
02/14/2019 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by CBELL1 - Both trash enclosures footings are OK to pour |
07/24/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
07/24/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
08/23/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
08/06/2019 | ENGR Grading Final | DROBERTS | Continued | Entered by DMERANZ1 - WALKED THE SITE TO CHECK ON THE SPECIFICATIONS FOR THE ROCK RIP RAP AND ITS INFIELD PLACEMENT. |
07/24/2019 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - |
07/15/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Final grading of parking area and installing sidewalks and curbs. |
05/24/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Contractor is installing site utilities. |
03/14/2019 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by CBELL1 - Trash enclosure walls are ready for grout to 6 feet. Contractor has started to install storm water controls. I reminded Dave that he needs to clean the street and post his address and SWPPP signage. |
02/28/2019 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by CBELL1 - Trash enclosure walls to 4 feet with a bond beam and ladder wire and steal at 32 inches and in corners |
02/14/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by CBELL1 - Project is well underway, buildings are being installed |