| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | ENGR Grading Final | Not Ready | ||
| 10/27/2022 | ENGR Grading Final | Not Ready | ||
| 07/22/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Note, Inspector recommends changing status to final as engineering final inspection was approved by Rdld |
| 08/18/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by JSCHNEI2 - Continue. No activity on site. |
| 06/25/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Continue. No grading activity at this time. |
| 06/01/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Continue. Working on ramp and sidewalks. |
| 04/20/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Working on utilities. 0 |
| 03/20/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by SFLORES2 - Grading contractor working on utilities at this time. |
| 02/10/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by DMERANZ1 - No grading activity at this time. Grading work has been performed for rough grading some other time. |
| 10/27/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by PAHUMAD1 - Continue. Gate locked no activity on site. |
| 09/21/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by JSCHNEI2 - Continue. Gate locked no activity on site. |
| 09/15/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by JSCHNEI2 - Continue. No grading activity at this time construction fence has been installed. |
| 07/14/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by JSCHNEI2 - Continue. No grading activity on this site at this time. |
| 06/30/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Continue. No grading activity at this time. Sidewalk on south side of lot six slopes OK and private ramps slopes OK. |
| 06/24/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Continue. Ramps on south side of site has been installed sidewalk On southwest side of site installed. Drainage on east side of sight vertical concrete walls. |
| 06/17/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Continue. No grading activity at this time. |
| 06/09/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Continue. Working on asphalt and Streets. |
| 06/05/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Continue. Grading Rodeway working on east side of site. |
| 06/02/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Continue. Met with Rick on site from borderland working on curb ramps and sidewalks. |
| 06/01/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Working on sidewalks and Ramp. |
| 05/21/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Working on site Utilities. |
| 05/14/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - No grading activity at this time. |
| 05/04/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Continue. No grading activity at this time. |
| 04/20/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by RSALDAT1 - Rough grade on pads and streets. |
| 02/18/2020 | ENGR Grading Final | RLEDONNE | Continued | Entered by DMERANZ1 - No grading activity at this time. |
| 05/22/2024 | ENGR Grading Final | Partial Pass | Contractors at a new sidewalk and curb to the project per plan | |
| 06/06/2024 | ENGR Grading Final | Not Ready | ||
| 06/25/2024 | ENGR Grading Final | Partial Pass | Ok for a Level 4 TCO pending the next Inspection on 6/27/2024 | |
| 06/25/2024 | ENGR Grading Final | Partial Pass | See comments in the specific items | |
| 06/27/2024 | ENGR Grading Final | Not Ready | ||
| 06/27/2024 | ENGR Grading Final | Not Ready | Sidewalk and Driveways repairs still need to be done next week or the following week | |
| 08/01/2024 | ENGR Grading Final | Partial Pass | I stopped by the site at 8:30 this morning to meet with the contractor and nobody is available at this time. So I left the site and I will return later on this afternoon or this morning if possible. I return to the site at 10 o’clock this morning to meet with the contractor and determine what is left to be done. The contractor is forming for the remaining sidewalks and driveways and will have the forms completed by this afternoon. Will take photographs and send them to me. Once I have approved the formwork, they will try to pour this remaining concrete tomorrow so that all the flat work will be done. The remaining item that’s going to be left open will be the drainage basins to make sure that they get done according to the approved plans and that they’ve manicured the grass and plants within those basins so it’s not overgrown as it is. |
|
| 08/21/2024 | ENGR Grading Final | Not Ready | Started on the grading for sidewalks or paving | |
| 08/27/2024 | ENGR Grading Final | Partial Pass | ||
| 09/12/2024 | ENGR Grading Final | Passed | ||
| 09/12/2024 | ENGR Grading Final | Partial Pass | Minor landscaping area still need to be addressed on Bellevue for this site before it can be approved | |
| 10/03/2024 | ENGR Grading Final | Passed |