Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Not Ready
Inspection History: PDSD Site/Engineering Division - Landscaping
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
PDSD Site/Engineering Division - Landscaping |
|
Not Ready |
|
| 10/27/2022 |
PDSD Site/Engineering Division - Landscaping |
|
Not Ready |
|
| 05/22/2024 |
PDSD Site/Engineering Division - Landscaping |
|
Not Ready |
Contractors that started on the landscaping in |
| 06/13/2024 |
PDSD Site/Engineering Division - Landscaping |
|
Not Ready |
Contractor has not started the landscape |
| 06/27/2024 |
PDSD Site/Engineering Division - Landscaping |
|
Passed |
|
| 06/28/2024 |
PDSD Site/Engineering Division - Landscaping |
|
Partial Pass |
Complete all the landscape areas in the basins and complete all sidewalks and driveways as they need to be prepared throughout the site prior to calling, and that’s final inspection. Once all DG has been placed. |
| 08/21/2024 |
PDSD Site/Engineering Division - Landscaping |
|
Not Ready |
Contractor hasn’t started landscaping |
| 10/03/2024 |
PDSD Site/Engineering Division - Landscaping |
|
Passed |
|