Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - DP18-0124
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/25/2019 | ENGR Engineering Final | BBENEDON | Approved | Entered by DMERANZ1 - |
10/28/2019 | ENGR Engineering Final | BBENEDON | Denied | Entered by DMERANZ1 - Letter provided from merchant design group through Epstein construction does not specify that the new pedestrian pathway is existing. The grading correction at the northwest corner has not been corrected to my satisfaction, I have asked Dave Roberts for direction in this matter and have sent him pictures of the job site and the job plans. It appears as though the new retention area specified in note number four has not been fully constructed, also The work specified in note 21 has not been completed. |
10/25/2019 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Engineering is OK for a temporary certificate. This is a courtesy return inspection for Ed with Epstein. Accessible walkways have been corrected. Complete the drainage correction, complete ground covering installations and stake the large trees as specified. Provide letter of clarification for new accessible path through existing asphalt leading to existing building as shown. Existing asphalt is out of compliance for accessibility. |
10/24/2019 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Engineering has no issues that would prevent a temporary certificate of occupancy. Complete the corrections for the accessible path and for the drainage issues, complete all landscaping and ground coverings. Remove construction debris and material stock piles from parking lot. Superintendents for the shell, the DP and the superintendent for the TI have been instructed to schedule final inspections as needed. |
10/21/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Correct slope on accessible path from street and install new accessible path to existing buildings as shown. Correct the grading at the north west corner of the parking lot. The landscaped area shall be lower than the curb cut. Remove excess dirt and debris from landscape areas prior to installing Dg. Terminate SWPPP if applicable. Schedule shell and building final inspections with the DP permit when you are ready for a temporary certificate. |
11/25/2019 | ENGR Engineering Final | BBENEDON | Approved | Entered by DMERANZ1 - |
11/22/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Meeting with desert earth to discuss work to be completed at nw drainage inlet. |
11/21/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - I spoke Scott from desert earth about the basin required. There is some water puddled in the parking lot. It’s been several hours since it rained. |
10/28/2019 | ENGR Engineering Final | BBENEDON | Denied | Entered by DMERANZ1 - Letter provided from merchant design group through Epstein construction does not specify that the new pedestrian pathway is existing. The grading correction at the northwest corner has not been corrected to my satisfaction, I have asked Dave Roberts for direction in this matter and have sent him pictures of the job site and the job plans. It appears as though the new retention area specified in note number four has not been fully constructed, also The work specified in note 21 has not been completed. |
10/25/2019 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Engineering is OK for a temporary certificate. This is a courtesy return inspection for Ed with Epstein. Accessible walkways have been corrected. Complete the drainage correction, complete ground covering installations and stake the large trees as specified. Provide letter of clarification for new accessible path through existing asphalt leading to existing building as shown. Existing asphalt is out of compliance for accessibility. |
10/24/2019 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Engineering has no issues that would prevent a temporary certificate of occupancy. Complete the corrections for the accessible path and for the drainage issues, complete all landscaping and ground coverings. Remove construction debris and material stock piles from parking lot. Superintendents for the shell, the DP and the superintendent for the TI have been instructed to schedule final inspections as needed. |
10/21/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Correct slope on accessible path from street and install new accessible path to existing buildings as shown. Correct the grading at the north west corner of the parking lot. The landscaped area shall be lower than the curb cut. Remove excess dirt and debris from landscape areas prior to installing Dg. Terminate SWPPP if applicable. Schedule shell and building final inspections with the DP permit when you are ready for a temporary certificate. |