Inspection History Details
Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
Permit Number - DP18-0120
Inspection Description - SITE - Stormwater Follow-up
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/14/2019 | SITE - Stormwater Follow-up | BBENEDON | Approved | Entered by DMERANZ1 - |
09/10/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - Landscaper has a large pile of dirt blocking public alley. |
08/23/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - I spoke with superintendent Dave about cleaning and keeping the sidewalks And streets clean of dirt and construction debris prior to the end of the day. |
08/22/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - Contractor is installing final grade, and perimeter fencing. Temporary fencing has been removed. No issues at this time, the only concern is keeping the sidewalks clear from dirt. |
07/15/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - Contractor needs to remove the mud and dirt from the streets around the project. |
05/24/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - Minor track out to be noted. Also perimeter fencing is being pushed over by dirt piles the south end of the site. |
04/10/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - There are no concerns at this time |
04/01/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - Controls have been installed there are no issues at this time. |
03/14/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - there is minor check out in the street to be noted |
02/19/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - There’s quite a bit of muddy track out due to the recent rains in the muddy conditions of the site. |
02/14/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - Minor track out onto Drachman . Superintendent has been asked to keep the streets clean. |