Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: DP18-0119

Parcel: 14111024C


Addresses:

8000 S RITA RD

Inspection Status: Complete (Recurring)

Inspection History: SITE - Stormwater Follow-up

Date Description Inspector Results Comments
12/01/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by PAHUMAD1 - Continue. No concerns at this time.
11/17/2020 SITE - Stormwater Follow-up RDELONNE Continued Entered by PAHUMAD1 - Continue. No concerns at this time.
11/05/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by PAHUMAD1 - Continue. No concerns at this time.
10/28/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RSALDAT1 - Continue. No concerns at this time.
09/28/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by JSCHNEI2 - Continue. No concerns at this time no Grading activity on site.
09/18/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RSALDAT1 - Continue. No concerns at this time. No grading activity.
08/27/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by JSCHNEI2 - Continue. No concerns at this time.
08/04/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RSALDAT1 - Continue. No concerns at this time.
07/30/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by JSCHNEI2 - Continue .No concerns at this time..
07/06/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by JSCHNEI2 - Continue. No concerns at this time.
05/04/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RSALDAT1 - No concerns at this time
08/08/2019 SITE - Stormwater Follow-up RLEDONNE Continued Entered by DMERANZ1 - Met with general contractor on site mentioned dead trees in nursery he said landscape architect was workingOn how to replace with the city. No concerns other than that.
06/06/2019 SITE - Stormwater Follow-up RLEDONNE Continued Entered by DMERANZ1 - No concerns at this time. Working on entrance no track out rock at this time Will do what’s needed to keep streets clean.
05/30/2019 SITE - Stormwater Follow-up RLEDONNE Continued Entered by DMERANZ1 - Met with grading contractor on site need to set up for concrete washout. Provide more rock at the entrance for track out.
05/28/2019 SITE - Stormwater Follow-up BBENEDON Continued Entered by CBELL1 -
04/29/2019 SITE - Stormwater Follow-up RLEDONNE Continued Entered by CBELL1 - No concerns at this time
04/09/2019 SITE - Stormwater Follow-up RLEDONNE Continued Entered by CBELL1 - Met with general contractor on site walk so I switch controls have been added no concerns at this time.
02/11/2019 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.
02/05/2019 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.
12/28/2018 SITE - Stormwater Follow-up DROBERTS Continued Entered by DROBERT5 - THERE ARE NO CONCERNS AT THIS TIME FOR THIS SITE. THERE ARE NO SIGNS OF TRACKOUT ON THE LOCAL ADJACENT STREETS, AND ALL THE EXISTING STORMWATER CONTROLS REMAIN INTACT.
12/21/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by CBELL1 - Make repairs on Southeast side of site for swppp controls.
12/12/2018 SITE - Stormwater Follow-up RLEDONN1 Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
12/06/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
11/30/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS.
11/20/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS.
11/16/2018 SITE - Stormwater Follow-up RLEDONN1 Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
11/05/2018 SITE - Stormwater Follow-up RLEDONN1 Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
10/08/2018 SITE - Stormwater Follow-up BBENEDON Continued Entered by VFLORES1 - Controls are in place and there are no issues at this time
09/26/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS
09/18/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.
09/14/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 -
09/10/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
09/07/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - WORKING ON INSTALLING SWPPP CONTROLS.