| 12/01/2020 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by PAHUMAD1 - Continue. No concerns at this time.
|
| 11/17/2020 |
SITE - Stormwater Follow-up
|
RDELONNE |
Continued |
Entered by PAHUMAD1 - Continue. No concerns at this time. |
| 11/05/2020 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by PAHUMAD1 - Continue. No concerns at this time. |
| 10/28/2020 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RSALDAT1 - Continue. No concerns at this time. |
| 09/28/2020 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by JSCHNEI2 - Continue. No concerns at this time no Grading activity on site.
|
| 09/18/2020 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RSALDAT1 - Continue. No concerns at this time. No grading activity.
|
| 08/27/2020 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by JSCHNEI2 - Continue. No concerns at this time.
|
| 08/04/2020 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RSALDAT1 - Continue. No concerns at this time. |
| 07/30/2020 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by JSCHNEI2 - Continue .No concerns at this time..
|
| 07/06/2020 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by JSCHNEI2 - Continue. No concerns at this time. |
| 05/04/2020 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RSALDAT1 - No concerns at this time |
| 08/08/2019 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by DMERANZ1 - Met with general contractor on site mentioned dead trees in nursery he said landscape architect was workingOn how to replace with the city. No concerns other than that. |
| 06/06/2019 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by DMERANZ1 - No concerns at this time. Working on entrance no track out rock at this time Will do what’s needed to keep streets clean. |
| 05/30/2019 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by DMERANZ1 - Met with grading contractor on site need to set up for concrete washout. Provide more rock at the entrance for track out. |
| 05/28/2019 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by CBELL1 - |
| 04/29/2019 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by CBELL1 - No concerns at this time |
| 04/09/2019 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by CBELL1 - Met with general contractor on site walk so I switch controls have been added no concerns at this time. |
| 02/11/2019 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME. |
| 02/05/2019 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME. |
| 12/28/2018 |
SITE - Stormwater Follow-up
|
DROBERTS |
Continued |
Entered by DROBERT5 - THERE ARE NO CONCERNS AT THIS TIME FOR THIS SITE. THERE ARE NO SIGNS OF TRACKOUT ON THE LOCAL ADJACENT STREETS, AND ALL THE EXISTING STORMWATER CONTROLS REMAIN INTACT. |
| 12/21/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by CBELL1 - Make repairs on Southeast side of site for swppp controls. |
| 12/12/2018 |
SITE - Stormwater Follow-up
|
RLEDONN1 |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 12/06/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 11/30/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS. |
| 11/20/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS. |
| 11/16/2018 |
SITE - Stormwater Follow-up
|
RLEDONN1 |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 11/05/2018 |
SITE - Stormwater Follow-up
|
RLEDONN1 |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 10/08/2018 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by VFLORES1 - Controls are in place and there are no issues at this time |
| 09/26/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS |
| 09/18/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME. |
| 09/14/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - |
| 09/10/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 09/07/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - WORKING ON INSTALLING SWPPP CONTROLS. |