Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/09/2019 | SITE - Stormwater Follow-up | BBENEDON | Approved | Entered by DMERANZ1 - |
05/30/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - There is work being performed at jobsite entrances, check out protection has been removed. |
05/14/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - Martin Luther King Jr. Way is closed down at this time. There are no stormwater control issues. |
04/02/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - There are no issues or concerns at this time.Minor track out noted on ML King Junior Way and on Tucson marketplace. |
03/14/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - There is quite a bit of a track out on Martin Luther King Way |
02/28/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - I spoke with the general contractor about correcting the track out protection and cleaning the streets |
02/22/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - There are no issues at this time. |
02/20/2019 | SITE - Stormwater Follow-up | bbenedo1 | Continued | Entered by BBENEDO1 - T%here is quite a bit of dirt on the streets, however the large chunks have been swept |
01/30/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - My only concern is the existing catch basin on the far west side at the HDPE connection, protecting contain dirt prior to this evening’s rain to prevent dirt from filling catch basin. |
01/25/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - |
01/24/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - Some track out onto MLK JR way. |
01/22/2019 | SITE - Stormwater Follow-up | BBENEDON | Correction Required | Entered by VFLORES1 - No concerns at this time. |
01/18/2019 | SITE - Stormwater Follow-up | bbenedo1 | Continued | Entered by BBENEDO1 - Miner track out noted |
01/17/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - Miner track out noted |
01/16/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - |
01/15/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by CBELL1 - No issues at this time, I suggest adding some rock at the 2in open drain pipe on the West End prior to tonight's rain. |
01/08/2019 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by DROBERT5 - NO REAL CONCERNS AT THIS TIME. THE CONTRACTOR HAS BEEN ADVISED TO CLEANUP THE MINOR TRACKOUT NOTED ON M L KING JR WAY, THIS WILL START TONIGHT WHEN THE SWEEPERS ARE AVAILABLE. |