Inspection History Details
Inspection Status: Not Ready
Inspection History: PDSD Site/Engineering Division - Landscaping
Permit Number - DP18-0104
Inspection Description - PDSD Site/Engineering Division - Landscaping
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | PDSD Site/Engineering Division - Landscaping | Not Ready | ||
05/13/2021 | PDSD Site/Engineering Division - Landscaping | MHERNANDEZ | Partial Approval | Entered by VLEON1 - PARTIAL THERE IS ONE PLANT MISSING |
11/06/2019 | PDSD Site/Engineering Division - Landscaping | DROBERTS | Partial Approval | Entered by DROBERT5 - COMPLETE ALL THE LANDSCAPING FOR THI SITE PRIOR TO CALLING IN ANOTHER INSPECTION, THIS WILL INCLUDE THE FOLLOWING BUT IS NOT LIMITED TO: 1) ENSURE ALL PLANTS HAVE BEEN INSTALLED, PORTIONS OF THE SITE WILL BE CHECKED AGAINST THE APPROVED PLANS. 2) COMPLETE THE PLACEMENT OF ALL ROCK RIP AND DECOMPOSED GRANITE AS SHOWN ON THE APPROVED PLANS. 3) ENSURE THAT ALL OF THE TREES HAVE BEEN STAKED AS SHOWN ON THE APPROVED PLANS. IT HAS BEEN NOTED AT THIS TIME THERE ARE TREES THROUGHOUT THE SITE THAT STILL HAVE THE NURSARY STAKES OR JUST A SINGLE POLE STAKE.IF STAKING OF A PLANT IS REQUIRED FOR A TREE IT MUST BE DONE IN THE MANNER THAT IS SHOWN ON THE LANDSCAPE DETAILS FOR TREE STAKING. 4) PROVIDE A MONITORING LETTER FROM THE LANDSCAPE ARCHITECT FOR ANY/ALL CHANGES TO THE SITE IN REGARDS TO THE NPPO. |
07/09/2019 | PDSD Site/Engineering Division - Landscaping | BBENEDON | Approved | Entered by DMERANZ1 - |
06/24/2019 | PDSD Site/Engineering Division - Landscaping | BBENEDON | Continued | Entered by DMERANZ1 - Contractor is landscaping in the areas close to the building main entrance. 09027 engineering final inspection. Not ready. Engineering has no issues preventing a TCO |
05/14/2019 | PDSD Site/Engineering Division - Landscaping | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - no landscaping has been installed at this time. |
11/06/2019 | PDSD Site/Engineering Division - Landscaping | DROBERTS | Approved | Entered by DROBERT5 - |
11/06/2019 | PDSD Site/Engineering Division - Landscaping | DROBERTS | Continued | Entered by DROBERT5 - COMPLETE ALL OF THE LANDSCAPING AS SHOWN ON THE APPROVED PLANS. THIS WILL ALSO INCLUDE THE PROPER STAKING OF ALL THE TREES, VERIFYING THAT ALL OF THE PLANTS HAVE BEEN INSTALLED AND ARE VIABLE, INSTALLATION OF ALL OF THE RIP RAP, AND THE SPRAYING OF HYDROSEED IN ALL DISTURBED AREAS ALONG THE OUTER PERIMETERS. |
08/27/2019 | PDSD Site/Engineering Division - Landscaping | BBENEDON | Continued | Entered by DMERANZ1 - Contractor is installing landscaping and riprap along the west and north perimeter’s of the site. |
08/20/2019 | PDSD Site/Engineering Division - Landscaping | BBENEDON | Continued | Entered by DMERANZ1 - Contractor is installing landscaping and riprap along south property line. |
07/12/2019 | PDSD Site/Engineering Division - Landscaping | BBENEDON | Partial Approval | Entered by DMERANZ1 - Contractor is installing landscaping in the south half of the site. Islands have been depressed as required and riprap has been installed at curb openings. |