Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP18-0089
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/04/2021 | ENGR Grading Final | BBENEDON | Approved | Entered by VLEON1 - Approved FOR 19 NORRIS - Please final permit if not already. All inspections were approved at time of construction |
04/23/2021 | ENGR Grading Final | BBENEDON | Approved | Entered by VLEON1 - Approved FOR 19 N NORRIS AV. Please final this permit if not already. All inspections were approved at time of construction. |
04/22/2021 | ENGR Grading Final | BBENEDON | Approved | Entered by VLEON1 - Approved. Please close this permit as all inspections have been completed and approved. |
09/23/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by VFLORES1 - |
09/23/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by VFLORES1 - |
09/23/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by VFLORES1 - |
01/09/2019 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - THIS INSPECTION HAS BEEN SCHEDULED FOR THE BUILDING FOOTERS, HAVE ADVISED GARY THAT WE CAN NOT PERFORM THE INSPECTION, IT HAS TO BE DONE BY ONE OF THE BUILDING INSPECTORS. |
01/07/2019 | ENGR Grading Final | DROBERTS | Not ready for Inspection | Entered by DROBERT5 - THIS INSPECTION IS NOT READY AT THIS TIME. CURRENTLY THE WORK FOR THIS SITE IS FOR THE BUILDING FOOTER AND NOT FOR THE TRASH ENCLOSURE. HAVE ADVISED THE CONTRACTOR TO RESCHEDULE THIS INSPECTION WHEN THEY ARE SETTING THE REBAR FOR THE TRASH ENCLOSURE. THE CURRENT FOOTER WORK IS TO BE INSPECTED UNDER THE COMBO PERMIT FOR THIS SITE. |
09/27/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - The general contractor Gary promises to clean the remaining construction debris from the demo which is in the city right of way. |
09/23/2019 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by VFLORES1 - Gary the general contractor canceled inspections. |
09/12/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Contractors doing work in the right of way and also landscaping on site. |
09/04/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Met with Keven and Gary general contractor. We looked at the plans and it appears that the water harvesting areas still needTo be enlarged. Gary stated that the property line is 2 feet closer and thanshown. I advised him to begin the depressed area at the property line and taper down to the required depth in the center of the water harvesting infiltration area. |
08/22/2019 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Contractor is working on final grade, has not started landscaping. |
08/14/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Contractor is preparing parking lot and driveways for asphalt. |
07/31/2019 | ENGR Grading Final | RLEDONNE | Continued | Entered by DMERANZ1 - Met with GC on site went over parking area. |