Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 09/27/2019 |
ENGR Engineering Final
|
BBENEDON |
Approved |
Entered by DMERANZ1 - The general contractor Gary promises to clean the remaining construction debris from the demo which is in the city right of way. |
| 09/23/2019 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by VFLORES1 - Gary the general contractor canceled inspections. |
| 08/14/2019 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - I went over, with Gary the superintendent, some of the requirements for final approval; including a letter from the engineer of record for the trash enclosure installed without engineering inspections. We also talked about stabilization of all disturb soils |
| 09/27/2019 |
ENGR Engineering Final
|
BBENEDON |
Approved |
Entered by DMERANZ1 - The general contractor Gary promises to clean the remaining construction debris from the demo which is in the city right of way. |
| 09/23/2019 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by VFLORES1 - Gary the general contractor canceled inspections. |
| 09/03/2019 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - |
| 08/27/2019 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - Contractor still needs to do final grading for landscape areas. Also striping parking area |