Permit: DP18-0060

Parcel: 99999999A


Addresses:

8525 E 22ND ST

Inspection Status: Not Ready

Inspection History: ENGR Engineering Final

Date Description Inspector Results Comments
10/27/2022 ENGR Engineering Final Not Ready
08/20/2020 ENGR Engineering Final RLEDONNE Approved Entered by RSALDAT1 - Approved.
03/12/2020 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by SFLORES2 - All work on development package must be complete before Engineering final.
11/12/2020 ENGR Engineering Final DROBERTS Partial Approval Entered by DROBERT5 - COMPLETE ALL PLANTING, REMOVE ALL NURSARY STAKES ONCE THE TREES ARE COMPLETE AND SCHEDULE ALL FINAL INSPECTIONS.
08/20/2020 ENGR Engineering Final RLEDONNE Continued Entered by RSALDAT1 - Complete all notes from other inspections. Complete all work on approved development package before calling for grading final.
02/10/2020 ENGR Engineering Final DROBERTS Continued Entered by DMERANZ1 - CONTACTED BRIAN AND TALKED ABOUT WHAT THEY WERE LOOKING FOR DURING THIS SITE VISIT. AS THE CONTRACTOR THEY ARE LOOKING TO CLOSE OUT THE PROJECT AND THEIR PERMIT. I HAVE ADVISED THEM THAT ALL THE COMMON AREA WORK NEEDS TO BE COMPLETED PER THE APPROVED AND A BOND NEEDS TO BE PUT IN PLACE FOR THE SUBDIVISION FOR ALL THE REMAINING ASSURABLE ITEMS. HE ADVISED ME THAT A BOND HAS BEEN SUBMITTED BUT HAS NOT BEEN FULLY APPROVED, SO IT IS NOT POSSIBLE TO CLOSEOUT THIS PROJECT FULLY AT THIS TIME. I WILL CHECK WITH JOHN VAN WINKLE TO SEE AT WHAT STAGE IN THE APPROVAL PROCESS WE ARE AT WITH THEBOND.
11/25/2019 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by DMERANZ1 - Complete all grading work on approved plans before calling for final grading.
10/18/2019 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by DMERANZ1 - Complete all work on development package plans.
11/15/2023 ENGR Engineering Final Passed