Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 11/18/2019 |
ENGR Grading Final |
RLEDONNE |
Approved |
Entered by DMERANZ1 - |
| 03/04/2019 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by CBELL1 - Matt for trashing closure OK. |
| 12/13/2018 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by CBELL1 - Vertical rebar and bond Beam for trash enclosure okay |
| 12/12/2018 |
ENGR Grading Final |
RLEDONN1 |
Continued |
Entered by RLEDONN1 - WORKING ON WALL FOR TRASH ENCLOSUER . |
| 11/27/2018 |
ENGR Grading Final |
RLEDONNE |
Partial Approval |
Entered by CBELL1 - Footer for trash enclosure okay. |
| 11/18/2019 |
ENGR Grading Final |
RLEDONNE |
Approved |
Entered by DMERANZ1 - |
| 06/18/2019 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by DMERANZ1 - Walk site with GC went over work to be done for TCO. |
| 06/07/2019 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by DMERANZ1 - Walk site with GC checked some slopes on East side of site. |
| 06/06/2019 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by DMERANZ1 - Walk site with GC went over temporary ADA parking for TCO. |
| 05/29/2019 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by DMERANZ1 - Walk site with GC putting down AB working on first phase of site. |
| 05/07/2019 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by CBELL1 - Met with general contractor on site went over plans for ADA parking and temporary ADA parking. |
| 11/27/2019 |
ENGR Grading Final |
DROBERT5 |
Approved |
Entered by DROBERT5 - |
| 11/27/2019 |
ENGR Grading Final |
DROBERT5 |
Approved |
Entered by DROBERT5 - |