Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - DP18-0008
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/16/2020 | ENGR Engineering Final | DROBERTS | Approved | Entered by RSALDAT1 - |
03/13/2020 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by SFLORES2 - Complete all work shown on your city approved development package plans. Sidewalk scuppers, riprap, ADA parking signs, wheel stops etc. clean dirt from basin. Install basin depth gauges as shown. |
02/05/2020 | ENGR Engineering Final | BBENEDON | Continued | Entered by DMERANZ1 - Contractor is installing concrete driveways and sidewalks within the right of way and constructing the storage building in the rear. |
10/15/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - |
06/04/2020 | ENGR Engineering Final | DROBERTS | Approved | Entered by DROBERT5 - |
06/02/2020 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by RSALDAT1 - Not ready. No change since last inspection |
05/14/2020 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by RSALDAT1 - Not ready. Waiting for resolution of roof drain terminals. Unable to reach contractor, Joe. Not on site. Business is open and operational. |
04/16/2020 | ENGR Engineering Final | DROBERTS | Partial Approval | Entered by RSALDAT1 - IS PARTIAL PENDING THE APPROVAL FOR THE MODIFICATIONS OF THE DRAINS ON THE WEST SIDE OF THE MAIN BUILDING. THE OWNER IS GOING TO CONTACT THE ZONING AND ENGINEERING REVIEWERS TO SEE IF THEY WILL APPROVE THE PROPSED RED LINE CHANGES FOR THE SCUPPER MODIFICATIONS. |
03/13/2020 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by SFLORES2 - |
02/05/2020 | ENGR Engineering Final | BBENEDON | Continued | Entered by DMERANZ1 - Contractor is installing concrete driveways and sidewalks within the right of way and constructing the storage building in the rear. |
12/11/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Parking lot has been prepared for asphalt. |