Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - DP17-0284
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/29/2019 | ENGR Engineering Final | DROBERTS | Approved | Entered by DMERANZ1 - |
07/25/2019 | ENGR Engineering Final | DROBERTS | Partial Approval | Entered by DMERANZ1 - COMPLETE ALL WORK AS SHOWN ON THE APPROVED PLANS. 1) THIS WILL INCLUDED BUT NOT LIMITED TO THE RETENTION/DETENTION/WATER HARVESTING AREAS. 2) ON THE SOUTH SIDE OF THE SITE IN THE WESTERN HALF THE DRAINAGE SWALE IT HAS BEEN NOTED ON THIS DATE THERE IS SETTLEMENT OF THE BOTTOM OF THE BASIN OF APPROXIMATELY 1 FOOT IN DEPTH. THE CONTRACTOR HAS BEEN ADVISED AND SHOWN THE AREA SO THEY CAN DETERMINE WHAT IS WRONG AND THEN MAKE THE CORRECTIONS AS DETERMINED BY THE ENGINEER OF RECORD. PROVIDE THIS DEPARTMENT WITH A REASON WHY THIS SETTLED AND WHAT IS THE SOLUTION FOR THE SETTLEMENT FROM THE ENGINEER OF RECORD. 3) THE NORTH ACCESS POINT IS NOT COMPLETED AS SHOWN ON THE APPROVED PLANS, EITHER CORRECT THIS WORK OR GET THIS ADDED ONTO THE REVISIONS FOR THE SITE 4) PROVIDE A SET OF APPROVED AS-BUILT DRAWINGS FOR ALL CHAGES THAT HAVE BEEN MADE TO THIS SITE, ALONG WITH A CERTIFICATION LETTER FROM THE ENGINEER OF RECORD FOR THIS SITE. 5)GENERAL SITE CLEANUP AND THE REMOVAL OF THE EXCESS EQUIPMENT, TOOLS, PORTABLE BINS AND ALL OTHER CONSTRUCTION EQUIPMENT. |
07/23/2019 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Provide a letter from the project engineer certified grade conformity. Riprap is only 4 inches deep, plan requires 8 inches. Depress water harvesting area number for 6 inches below curb opening as shown. Remove materials from sidewalk at curb repair. Jack with Canyon builders |
07/29/2019 | ENGR Engineering Final | DROBERTS | Approved | Entered by DMERANZ1 - |
07/25/2019 | ENGR Engineering Final | DROBERTS | Partial Approval | Entered by DMERANZ1 - COMPLETE THE REMAINING WORK ON THIS SITE PRIOR TO SCHEDULING ANOTHER INSPECTION. |
07/23/2019 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Provide a letter from the project engineer certified grade conformity. Riprap is only 4 inches deep, plan requires 8 inches. Depress water harvesting area number for 6 inches below curb opening as shown. Remove materials from sidewalk at curb repair. Jack with Canyon builders |