Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 08/11/2020 |
ENGR Grading Final |
RLEDONNE |
Approved |
Entered by JSCHNEI2 - Approved. |
| 04/13/2018 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) LOOKED AT THE FOOTINGS AND RE-BAR LAY OUT OF 2-48" SRP ALONG THE NORTH SIDE OF THE SITE.
2) FOOTING DIMENSIONS WERE 1' DEEP, 22' LONG AND 3' 8'.
#4 RE-BAR INSTALLED FOR HEAD-WALL FLOOR, EVENLY SPACED PER ADOT 6.30 #205.
3) PICTURES TAKEN - OK FOR CONCRETE
|
| 08/11/2020 |
ENGR Grading Final |
RLEDONNE |
Approved |
Entered by JSCHNEI2 - Approved. |
| 12/11/2019 |
ENGR Grading Final |
RLEDONNE |
Approved |
Entered by DMERANZ1 - |
| 09/11/2020 |
ENGR Grading Final |
RLEDONNE |
Approved |
Entered by JSCHNEI2 - Approved. |
| 08/19/2020 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by JSCHNEI2 - Continue. Appear to be working on south side of buildings starting cleanup and adding riprap per approved plan. |
| 06/18/2020 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RSALDAT1 - Continue. Have installed asphalt around building and working on fencing on south side of buildings. |
| 05/20/2020 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RSALDAT1 - Continue. Working on grading access road around buildings. |
| 12/11/2019 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by DMERANZ1 - Met with Ashton general contractor and Dave Roberts on site. Dave is going back to office to get with John Vanwinkle about this inspection. |
| 12/11/2019 |
ENGR Grading Final |
RLEDONNE |
Approved |
Entered by DMERANZ1 - |