Permit: DP17-0267

Parcel: 14002002C


Addresses:

3950 E IRVINGTON RD

Inspection Status: Passed

Inspection History: SITE - Stormwater Follow-up

Date Description Inspector Results Comments
11/18/2021 SITE - Stormwater Follow-up DROBERTS Approved Entered by DROBERT5 -
11/10/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by PAHUMAD1 - Continue. No concerns at this time.
10/29/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RSALDAT1 - Continue. No concerns at this time.
10/21/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RSALDAT1 - Continue. No changes from last inspection.
09/30/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RSALDAT1 - Continue. No changes from last inspection.
09/09/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by JSCHNEI2 - Continue. Contractor working on getting debris from riprap.On South East side of sight.
08/11/2020 SITE - Stormwater Follow-up RLEDONNE Approved Entered by JSCHNEI2 - Approved.
08/04/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RSALDAT1 - Continue. Rip rap on south side of center building has been cleaned. Other drainage areas have not been clean. Working on drainage on north and south side of building.
07/13/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by JSCHNEI2 - Continue. Silt building up in riprap at Inlets and outlets of pipe.
06/18/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RSALDAT1 - Continue. Open areas of drain where pipes make change of directions still need to be clean. Appear to be working in the most southwestern change of direction before railroad tracks.
05/20/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RSALDAT1 - Continue. GC send photos showing that he added waddle at exit pipes. Until he gets a chance to clean sediment from rip rap after relocating water pipes.
04/30/2020 SITE - Stormwater Follow-up RLEDONNE Not ready for Inspection Entered by RSALDAT1 - Not ready. GC was not ready for inspection.
04/16/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RSALDAT1 - Waiting for photos from general contractor.
04/02/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by SFLORES2 - No concerns at this time.
03/19/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by SFLORES2 - Met with Alan from Ashton construction went over controls that need repaired.
03/05/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by DMERANZ1 - No concerns at this time with controls silt still needs to be cleaned from riprap at all inlets and outlets.
02/20/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by DMERANZ1 - Went over minor corrections with Ashton’s super Alan.
02/06/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by DMERANZ1 - Walk site waddle still in place. Still have not cleaned settlement.
01/23/2020 SITE - Stormwater Follow-up RLEDONNE Continued Entered by DMERANZ1 - Controls in place of catch basins. Talk to Alan site manager about Mud starting to build up in basins.
01/09/2020 SITE - Stormwater Follow-up DROBERTS Continued Entered by DMERANZ1 - NO CONCERNS AT THIS TIME FOR THIS SITE.
12/18/2019 SITE - Stormwater Follow-up RLEDONNE Continued Entered by DMERANZ1 - Controls have been added inlet pipes. Talk to Rex from Ashton about silt needs to be removed from riprap and erosion issuesOn unstabilized banks.
12/11/2019 SITE - Stormwater Follow-up RLEDONNE Continued Entered by DMERANZ1 - Walk site with Dave Roberts check notes from Dave Roberts