Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Grading Final
Permit Number - DP17-0266
Inspection Description - ENGR Grading Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
05/04/2021 | ENGR Grading Final | BBENEDON | Denied | Entered by VLEON1 - Denied. Note, per DR, building official needs to approve lack of access from speedway as well as trash and closure not inspected. University Commons phase 1 Canyon builders |
11/19/2018 | ENGR Grading Final | bbenedo1 | Continued | Entered by BBENEDO1 - Begin over ex for new building. |
10/25/2018 | ENGR Grading Final | BBENEDON | Continued | Entered by CBELL1 - there is dirt work in progress on vacant lot east of paved parking area |
09/17/2018 | ENGR Grading Final | bbenedo1 | Continued | Entered by BBENEDO1 - Grading for pavement and curbs. Provide trackout protection at east entrance. |
10/25/2018 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by CBELL1 - |
11/09/2018 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by CBELL1 - okay for grout, provide cleanouts |
11/07/2018 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by CBELL1 - footings and bollards okay for concrete. |
11/06/2018 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by CBELL1 - a.m. inspection requested and provided, contractor still Excavating for trash enclosures no rebar has been installed yet. I provided our hand out to the GC and instructed him to reschedule for the inspection when they are ready. |
10/25/2018 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by CBELL1 - use this inspection code for your trash enclosure |
11/19/2018 | ENGR Grading Final | bbenedo1 | Continued | Entered by BBENEDO1 - Contractor preparing to install rip rap in north basin. Preparing Speedway entrance for pavement. |
11/06/2018 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by CBELL1 - not ready at 8:30 a.m., contractor Excavating for trash and closure at this time. |
10/30/2018 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by CBELL1 - Courtesy inspection for Rick and Christian with Canyon builders. Four-for-four 7979. Contractors are correcting the pedestrian access slope issues from 6th Avenue. Rick engineering is on site. We also have slope issues at the lower corner of the north most accessible parking space and the northernmost accessible striped pedestrian access. The Landscaping, retention basins, trash and closures, and access from Speedway Boulevard have not yet been installed. Building official approval will be necessary for a temporary C of o. |
10/25/2018 | ENGR Grading Final | BBENEDON | Continued | Entered by CBELL1 - contractor is installing concrete drive through |
09/19/2018 | ENGR Grading Final | bbenedo1 | Not ready for Inspection | Entered by BBENEDO1 - Still need track-out controls. |
09/17/2018 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by CMURPHY1 - Provide track out control at East entrance grading for pavement and curbs okay. Canyon building asked if they can get a TCO without vehicle access from Speedway and the trash enclosures. |
04/26/2018 | ENGR Grading Final | MRUSSO | Continued | Entered by DROBERT5 - NO SIGNIFICANT SITE CONCERNS AT THIS TIME |