Permit: DP17-0225

Parcel: 115211600


Addresses:

1714 W SPEEDWAY BL


Inspection Status: Passed

Inspection History: ENGR Engineering Final

Permit Number - DP17-0225

Inspection Description - ENGR Engineering Final

Inspection Status - Passed

Date Description Inspector Results Comments
12/27/2018 ENGR Engineering Final BBENEDON Approved Entered by CBELL1 -
12/20/2018 ENGR Engineering Final BBENEDON Not ready for Inspection Entered by CBELL1 - Move access I'll over to avoid obstacle at sidewalk ramp. Install bicycle parking.
12/18/2018 ENGR Engineering Final BBENEDON Not ready for Inspection Entered by CBELL1 -
12/14/2018 ENGR Engineering Final BBENEDON Not ready for Inspection Entered by CBELL1 - Spoke with Dale about remaining items including striping bicycle parking Landscaping and stabilization.
12/27/2018 ENGR Engineering Final BBENEDON Approved Entered by CBELL1 -
12/20/2018 ENGR Engineering Final BBENEDON Partial Approval Entered by CBELL1 - Engineering has no issues that would prevent a temporary C of O. Complete the work shown on plan
12/18/2018 ENGR Engineering Final BBENEDON Not ready for Inspection Entered by CBELL1 - Complete accessible parking and signage also accessible walkway. Complete riprap
12/13/2018 ENGR Engineering Final bbenedo1 Not ready for Inspection Entered by BBENEDO1 - I spoke with Dale about completion of remaining work