Permit: DP17-0211

Parcel: 128141380


Addresses:

5278 E 21ST ST

Inspection Status: Passed

Inspection History: ENGR Engineering Final

Date Description Inspector Results Comments
10/16/2017 ENGR Engineering Final DROBERT5 Approved Entered by DROBERT5 -
10/05/2017 ENGR Engineering Final DROBERTS Partial Approval Entered by DROBERT5 - THE SITE IS NOT COMPLETE AT THIS TIME FOR THE EXTERIOR WORK AND WILL BE HELD TILL ALL OF THE WORK IS COMPLETED.
10/04/2017 ENGR Engineering Final DROBERTS Partial Approval Entered by DROBERT5 - WALKED THE SITE WITH ALAN AND LOOKED OVER THE AREAS OF CONCERN THAT MIKE RAISED DURING YESTERDAYS INSPECTION OF THE COMBO PERMIT. I HAVE CONTACTED LOREN MAKUS AND STEVE SHIELDS, THEY HAVE PROVIDED ME WITH INSITE TO THE ADDITIONAL ITEMS THAT ARE NOT CHOWN ON THE APPROVED PLANS. THE SCUPPERS FOR THE SITE HAVE BEEN ADDED TO HELP ENSURE THAT THE POUNDING WATER WITHIN THE OPEN AREAS BETWEEN THE SIDEWALKS HAS A PLACE TO BE RELEASED RATHER THAN STAYING IN THE AREAS. THE AREA LOCATED AT THE SOUTHWEST CORNER OF THE SITE WILL BE THE LOCATION OF THE FUTURE PARKING. IT APPEARS THAT THE PARKING SIZE AND DIMENSIONS HAVE NOT CHANGED FROM WHAT WAS ORIGINALLY OUT ON THE SITE IN THE PAST. STEVE HAS ADVISED ME THAT IF THE EXISTING PARKING LOCATION HAS NOT GROWN IN SIZE THERE IS NOT A NEED FOR HIM TO REVIEW THE PLAN. THE FINAL INSPECTION FOR THIS SITE WILL NOT BE CALLED IN TILL ALL OF THE SITE WORK HAS BEEN COMPLETED AND IS READY FOR THE INSPECTION.