Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
Permit Number - DP17-0182
Inspection Description - PDSD Engineering Division Pre-Construction SITE
Inspection Status - Passed
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/05/2018 | PDSD Engineering Division Pre-Construction SITE | RLEDONNE | Approved | Entered by RLEDONN1 - |
| 02/23/2024 | PDSD Engineering Division Pre-Construction SITE | Not Ready | Latest plan revision is 2023. Contractor please provide contact information and schedule preconstruction meetings for work in progress. North east portion of site containing buildings 23 and four construction has started. Materials on site for stormwater piping and below ground basin construction. Contractor shall schedule inspections daily for below ground Stormwater work in progress. |
|
| 02/27/2024 | PDSD Engineering Division Pre-Construction SITE | Partial Pass | Patrick with Rio west has a new development package permit and plan for this project and will start scheduling inspections as required. | |
| 03/06/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | discussed several project details: HDPE backfill/trench width/depth, ADA parking, solid waste enclosure, etc. |