Inspection Status: Partial Pass
Inspection History: For trash and recycling enclosures
Permit Number - DP17-0182
Inspection Description - For trash and recycling enclosures
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/11/2025 | For trash and recycling enclosures | Partial Pass | Contractors OK to pour the footer for the trash closers two of them | |
| 02/18/2025 | For trash and recycling enclosures | Partial Pass | Contractors good to pour the floors for the both trash closers | |
| 02/23/2024 | For trash and recycling enclosures | Not Ready | ||
| 02/23/2024 | For trash and recycling enclosures | Not Ready | ||
| 03/04/2025 | For trash and recycling enclosures | Partial Pass | Contractors good to pour the second trash enclosure apron | |
| 03/19/2024 | For trash and recycling enclosures | Not Ready | ||
| 06/23/2025 | For trash and recycling enclosures | Partial Pass | Contractor is missing one number for vertical bar in front of the trash enclosure on the right hand side. Also, the contractor ordered the wrong bollards should’ve ordered 7 foot bollards not 6 foot bollards need to replace the bollards. | |
| 06/24/2025 | For trash and recycling enclosures | Partial Pass | Contractor, good to pour the footers with the bollards | |
| 07/03/2025 | For trash and recycling enclosures | Partial Pass | Vertical and horizontal reinforcement is in place. Plan to grout walls in a single lift, weep holes have been provided to verify flow. Okay to grout to full height. | |
| 07/07/2025 | For trash and recycling enclosures | Partial Pass | Rebar placement is good. Compaction is good. Form slope is good. Okay to pour slab for side-by-side refuse enclosure. | |
| 07/28/2025 | For trash and recycling enclosures | Partial Pass | Bldg 2, hotel, East refuse enclosure is complete and accurate to plans, passes inspection. | |