Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: DP17-0079

Parcel: 12407140A


Addresses:

55 N PARK AV

Inspection Status: Passed

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
07/08/2019 ENGR Grading Final BBENEDON Approved Entered by DMERANZ1 - Note all work was performed without city engineering inspection. A letter from the engineer of record for this project stating that all stormwater grading was installed as shown for the approved plans, for final approval of this project.
07/08/2019 ENGR Grading Final BBENEDON Approved Entered by DMERANZ1 - Note all work was performed without city engineering inspection. A letter from the engineer of record for this project stating that all stormwater grading was installed as shown for the approved plans, for final approval of this project.
07/08/2019 ENGR Grading Final BBENEDON Approved Entered by DMERANZ1 - Note all work was performed without city engineering inspection. A letter from the engineer of record for this project stating that all stormwater grading was installed as shown for the approved plans, for final approval of this project.
07/08/2019 ENGR Grading Final BBENEDON Approved Entered by DMERANZ1 - Note all work was performed without city engineering inspection. A letter from the engineer of record for this project stating that all stormwater grading was installed as shown for the approved plans, for final approval of this project.
10/20/2017 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - THE CONTRACTOR HAS REMOVED A MNAHOLE SHOWN ON SHEET 10 OF 24, BUT WAS NOT ABLE TO LOCATE THE SERVICE LINE TO THE MANHOLE FROM TYNDALL.