Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Engineering Final
|
|
Not Ready |
|
| 10/05/2017 |
ENGR Engineering Final
|
DROBERTS |
Partial Approval |
Entered by DROBERT5 - OK FOR A TEMPORARY CERTIFICATE OF OCCUPANCY, THE PREVIOUS NOTED HANDICAP ACCESS PROBLEMS HAVE BEEN COMPLETED AT THIS TIME. |
| 09/15/2017 |
ENGR Engineering Final
|
MRUSSO |
Denied |
Entered by DROBERT5 - 1) COMPLETE SITE CONSTRUCTION PER THE APPROVED PLAN
2) COMPLETE LANDSCAPING PER THE APPROVED PLAN
3) PROVIDE A CERT STATEMENT FORM THE ENG OF RECORD
4) PROVIDE AN APPROVED PLAN THAT SHOWS ANY AND ALL SITE CHANGES MADE DURING CONSTRUCTION FOR THE FINAL INSPECTION. |
| 08/21/2017 |
ENGR Engineering Final
|
MRUSSO |
Denied |
Entered by DROBERT5 - NO CHANGES FROM LAST INSPECTION |
| 08/04/2017 |
ENGR Engineering Final
|
MRUSSO |
Denied |
Entered by DROBERT5 - 1) PROVIDE AN APPROVED PLAN SHOWING ANY AND ALL CHANGES MADE TO THE SITE/GRADING/LANDSCAPING FOR FINAL INSPECTION.
2) PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT ALL SITE WORK WAS SUBSTANTIALLY COMPLETED PER THE APPROVED PLANS.
3) COMPLETE ALL CONSTRUCTION PER THE APPROVED PLANS
CALL FOR RE-INSPECTION |
| 12/28/2017 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO CHANGES, CALL FOR RE-INSPECTION |
| 10/12/2017 |
ENGR Engineering Final
|
MRUSSO |
Denied |
Entered by DROBERT5 - COMPLETE CONSTRUCTION PER THE APPROVED PLAN OR PROVIDE AN APPROVED PLAN THAT SHOWS WHAT WAS CONSTRUCTED |
| 10/02/2017 |
ENGR Engineering Final
|
DROBERTS |
Not ready for Inspection |
Entered by DROBERT5 - MET WITH ZACH FROM CANYON CONTRACTING AND LOOKED OVER WHAT IT WILL TAKE FOR THIS SITE TO APPROVE IT FOR A TEMPORARY CERTIFICATE OF OCCUPANCY FOR THE BUILDING AT THIS LOCATION. |
| 09/29/2017 |
ENGR Engineering Final
|
DROBERTS |
Not ready for Inspection |
Entered by DROBERT5 - I MET ZACH OUT ON SITE THIS MORNING TO SEE WHAT HE NEEDS TO HAVE COMPLETED PRIOR TO SEEKING A TCO FOR THIS SITE. FOLLOWING IS A LIST OF ITEMS THAT ARE NOT COMPLETED AT THIS TIME THAT WILL AFFECT THE ISSUANCE OF THE TCO:
1) THE EXISTING T.E.P. POWERPOLE REMAINS IN THE P.A.A.L. BETWEEN THE TWO STRUCTURES THIS WILL NEED TO BE REMOVED AND THE ELECTRICAL WILL NEED TO BE COMPLETED IN THE UNDERGROUND STRUCTURES. I HAVE DISCUSSED THE FENCING OFF OF THE AREAS DIRECTLY BENEATH THE WIRES AND APPROXIMATELY 5 FEET EAST AND WEST TO ALLOW FOR A PARTIAL USE OF THE PARKING LOT. THIS AREA WILL HAVE TO BE ENTERED AND EXITED FROM THE WEST ENTRANCE, THIS WILL BE DISCUSSED WITH CLAYTON BEFORE A FINAL DECISION IS MADE.
2) COMPLETE ANY MODIFICATIONS TO THE PLANS FOR ANY LANDSCAPE ITEMS, PROVIDE AN APPROVED REVISION TO THE SITE PLAN PRIOR TO PERFORMING ANY OF THIS WORK.
3) COMPLETE THE INSTALLATION OF THE WROUGHT IRON FENCING MATERIALS ADJACENT TO THE PARKING LOT, THIS WILL INCLUDE BUT IS NOT LIMITED TO ALL FENCE PANELS, GATE STRUCTURES, EMBLEMS, AND GATES (PEDESTRIAN AND VEHICULAR), AND THE PAINTING OF ALL MATERIALS.
4) COMPLETE THE TURF AND SHADE STRUCTURE AREA OR PROVIDE A BARRIER AROUND THE AREA THAT WILL STILL BE UNDER CONSTRUCTION.
5) CHECK THE RIGHT-OF-WAY ADJACENT AND SOUTH OF THE TRASH ENCLOSURES TO ENSURE THAT ALL OF THE TRASH ENCLOSURES AND THE SERVICE APPROACH SLABS ARE LOCATED WITHIN THE PRIVATE PROPERTY. IF POSTIONS OF THESE STRUCTURES ARE IN WITHIN THE CITYS RIGHTS-OF-WAY YOU MAY NEED TO SEEK A VARIENCE OR AN EASEMENT FOR THE USE OF THE AREA. CONTACT PATRICIA GEHLEN TO VERIFY THE LOCATION OF THE CITIES RIGHTS-OF-WAY PRIOR TO SEEKING THE FULL C OF O FOR THIS SITE. MAKE ALL NECESSARY REPAIRS TO ANY OF THE APPROACH SLABS THAT HAVE BEEN DAMAGED PRIOR TO THE FINALIZATION OF ALL INSPECTIONS.
6) COMPLETE ALL OF THE PEDESTRIAN GATES THROUGHOUT THE SITE, THIS WILL INCLUDE ALL OF THE GATES ON THE SOUTHSIDE OF THE PROPERTY AS WELL AS THE PEDESTRIAN ACCESS GATE AT THE NORTHWEST CORNER OF THIS SITE.
7) SPASH PADS FOR THE ROOF DRAINAGE PIPES HAVE NOT BEEN PROVIDED AT VARIOUS LOCATIONS WITHIN THIS SITE. INSTALL THESE IN ALL AREAS WHERE IT IS EVIDENT THAT EROSION MAY BE A ISSUE IN THE FUTURE.
8) ENSURE THAT ALL HANDRAILS HAVE BEEN INSTALLED ON THIS SITE AS REQUIRED. THIS WILL INCLUDE ALL RAMPS AND STAIRWAYS, THESE RAILS NEED TO MEET THE CODE REQUIREMENTS AT ALL LOCATIONS. IT HAS BEEN NOTED ON SOME OF THE RAMPS ON THE WEST SIDE OF THIS SITE THAT HEY ARE MISSING THE HANDRAIL EXTENSIONS AND THE LOWER BARS IN SOIME AREAS EXCEED THE MAXIMUM OPENNING LARGER THAT 4 INCHES ABOVED THE FINISH SURFACE OF THE SIDEWALK RAMPS.
9) THE ADA PARKING SPACE AND ACCESS AISLE EXCEED THE MAXIMUM 2% SLOPE, THESE AREAS WILL HAVE TO BE REWORKED SO THAT THEY FULL UNDER THE MAXIMUM SLOPE VALUE. |
| 09/15/2017 |
ENGR Engineering Final
|
MRUSSO |
Denied |
Entered by DROBERT5 - 1) COMPLETE SITE CONSTRUCTION PER THE APPROVED PLAN
2) COMPLETE LANDSCAPING PER THE APPROVED PLAN
3) PROVIDE A CERT STATEMENT FORM THE ENG OF RECORD
4) PROVIDE AN APPROVED PLAN THAT SHOWS ANY AND ALL SITE CHANGES MADE DURING CONSTRUCTION FOR THE FINAL INSPECTION. |
| 08/21/2017 |
ENGR Engineering Final
|
MRUSSO |
Denied |
Entered by DROBERT5 - NO CHANGES FROM LAST INSPECTION 8/4/17 |
| 08/04/2017 |
ENGR Engineering Final
|
MRUSSO |
Denied |
Entered by DROBERT5 - 1) PROVIDE AN APPROVED PLAN SHOWING ANY AND ALL CHANGES MADE TO THE SITE/GRADING/LANDSCAPING FOR FINAL INSPECTION.
2) PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT ALL SITE WORK WAS SUBSTANTIALLY COMPLETED PER THE APPROVED PLANS.
3) COMPLETE ALL CONSTRUCTION PER THE APPROVED PLANS
CALL FOR RE-INSPECTION |
| 07/11/2017 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) PRIOR TO C OF O AND FINAL APPROVAL, PROVIDE A CERTIFICATION STATEMENT FROM THE ENG OF RECORD AND A APPROVED PLAN SHOWING WHAT WAS BUILT
2) ENSURE COMPLIANCE WITH YOUR SWPPP THROUGHOUT CONSTRUCTION
3) CALL FOR INSPECTION FOR INSTALL OF 8' STORM PIPE |