Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
Permit Number - DP17-0038
Inspection Description - SITE - Stormwater Follow-up
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/07/2021 | SITE - Stormwater Follow-up | DROBERT5 | Approved | Entered by DROBERT5 - |
12/02/2021 | SITE - Stormwater Follow-up | DROBERTS | Partial Approval | Entered by DROBERT5 - MET WITH TOFEL CONSTRUCTION AND WALKED THE SITE TO SEE WHERE THEY ARE AT IN REGARDS TO A FINAL RELEASE. NO CONCERNS AT THIS TIME |
11/24/2021 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - Continued |
09/22/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Partial Approval | Entered by RSALDAT1 - PARTIAL /T.C.O |
09/21/2021 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by RSALDAT1 - CONTINUED AT THIS TIME. NO CONCERNS AT THIS TIME, THE SITE IS NOT READY. |
08/27/2021 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by RSALDAT1 - CONTINUED AT THIS TIME, NO CONCERNS NOTED DURING THIS INSPECTION |
07/27/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by RSALDAT1 - )CN / NEED TO ADDRESS THE DOWN SPOTS COMING OFF THE BUILDING. |
10/15/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by JSCHNEI2 - Continued. Work in right of way. Track out contained within right of way. West entrance has no protection |
10/15/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by JSCHNEI2 - Continued. Minor track outs noted Storage yard entrance west of project. |
09/21/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Minor track out noted. Also many broken sandbags used for barricade on Church Avenue. |
06/05/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Nic with Tofel, Underground utilities require building inspections. |
06/02/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Track out on Church Avenue. Also barricades installed in the right of way |
05/29/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - Continued. There is track out on church and no protections in place. Protections have been removed along the north side of the property on Broadway and the ground has not been stabilized. Please install/reinstall controls as required and necessary. Contact number provided was in accurate and I was unable to contact superintendent. |
02/26/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by SFLORES2 - No issues at this time |
12/05/2019 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by DMERANZ1 - NO CONCERNS AT THIS TIME FOR THIS SITE. MOST OF THE WORK AT THIS TIME IS ON THE NEW VERTICAL BUILDING CONSTRUCTION. NO SIGNS OF TRACK-OUT OR MATERIAL LEAVING THIS SITE. |
08/22/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - No issues at this time. Controls are in place. |
07/15/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - No issues at this time |
06/25/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - No issues at this time |
06/21/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - |
06/12/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - No issues at this time. |
06/05/2019 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by DMERANZ1 - NO CONCERNS NOTED DURING THIS INSPECTION, MINOR CLEANUP ON CHURCH THROUGH THE SITE SOUTH TOWARDS THE TCC PARKING AREA. |
05/31/2019 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by DMERANZ1 - NO CONCERNS OTHER THAN MINOR TRACK-OUT ONTO CHURCH, CONTRACTOR WILL SCHEDULE A SWEEPER FOR CLEANUP. |
05/22/2019 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - There is notable track out onto Church Avenue that needs to be corrected. Louis said he has ordered a street sweeper. The side entrance has changed there is no longer track out protection installed. We also have dirt on the south side walk That needs to be cleaned up, a couple of loose fence posts that need to be picked up and the privacy barrier needs to be reattached to the fence where it’s come loose. Thank you Brian |
04/29/2019 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by CBELL1 - NO CONCERNS AT THIS TIME. |
04/12/2019 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by CBELL1 - no site concerns noted during this walk through minor cleanup of Church Street has been advised to the Contractor. |
04/03/2019 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by CBELL1 - ALL WORK IS BEING MONITORED FOR ANY TRACKOUT. INSPECTION 9185 GRADING INTERMEDIATE IS CONTINUED T THIS TIME. THE CREWS ARE WORKING ON THE INSTALLATION OF STORM DRAIN PIPE AT THE NORTHWEST CORNER OF THE SITE SOUTH OF THE EXISTING RETAINING WALL. THEY WILL BE TAKING PHOTOS OF THIS AREA AND SEND THEM AS THEY PLACE ADDITIONAL BACKFILL OVER THE PIPES. ADDITIONAL INSPECTIONS WILL BE SCHEDULED AS NEEDED THROUGHOUT THIS OPERATION. |
03/22/2019 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by CBELL1 - The contractor is working on the installation of storm drains on the north side of the project and general site work throughout the project no concerns at this time |
03/04/2019 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by CBELL1 - No concerns at this time, I contacted David with TOFEL COSTRUCTION and asked if there was anything else we needed to look at. He advised that they needed to look at drainage items near Broadway, we will meet onsite tomorrow morning at 6:45 am. |