Permit: DP17-0038

Parcel: 11720016G


Addresses:

110 S CHURCH AV


Inspection Status: Passed

Inspection History: ENGR Engineering Final

Permit Number - DP17-0038

Inspection Description - ENGR Engineering Final

Inspection Status - Passed

Date Description Inspector Results Comments
12/03/2021 ENGR Engineering Final DROBERTS Approved Entered by DROBERT5 -
08/27/2021 ENGR Engineering Final DROBERTS Continued Entered by RSALDAT1 - CONTINUED, OK FOR A TCO STOCKING PURPOSES ONLY IN THE NORTH EAST CORNER OF THE BUILDING PENDING ALL OTHER INSPECTIONS. THE AREA THAT IS BEING CONSIDERED AT THIS TIME IS APPROXIMATELY 15 FEET NORTH OF THE NORTH EAST CORNER OF THE BUILDING AND SOUTH APPROXIMATELY 50 FEET SOUTH JUST PAST THE 1ST DOOR SOUTH OF THE MAIN ENTRANCE. THIS TCO HAS NOT BEEN REQUESTED FOR OPERATIONAL PURPOSES OR TO ALLOW THE GENERAL PUBLIC INTO THIS SITE.
01/10/2019 ENGR Engineering Final DROBERTS Continued Entered by DROBERT5 - I HAVE RESCHEDULED THIS INSPECTION TO TAKE PLACE ON 1/14/2019 WHEN BRYAN BENEDON IS AVAILABLE SO THAT THE WORK CAN PROCEED CORRECTLY
12/13/2021 ENGR Engineering Final DROBERTS Approved Entered by RSALDAT1 - APPROVED
08/27/2021 ENGR Engineering Final DROBERTS Not ready for Inspection Entered by RSALDAT1 - NOT READY AT THIS TIME, THERE IS TOO MUCH EXTERIOR WORK TO EVEN CONSIDER A PUNCH LIST AT THIS TIME. THIS SITE MAY BE READY TO LOOK AT A FINAL GRADING INSPECTION DURING THE LAST WEEK OF SEPTEMBER.