Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP16-0241
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/11/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by CBELL1 - Trash enclosure Matt and bollards are OK for concrete. |
04/09/2019 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by CBELL1 - GC Andy with Canyon. Contractor is installing one of the two rebar mat. The bollards are too short they are only 6 feet long. The standard requires 3 feet below grade and 4 feet above grade. Also block walls have not yet been grouted, inspection for pre-grout is required. |
11/28/2018 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by CBELL1 - Courtesy inspection for Andy Wilson. Trash enclosure number to footings are okay for concrete. Reschedule inspection for bollards and rebar mat. 09152 stormwater controls, not ready. I asked superintendent Andy Wilson at 312-1663 to install stormwater controls prior to the upcoming rain. |
11/21/2018 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by CBELL1 - South trash and closure footings are okay for concrete. |
07/03/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
07/03/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
08/20/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
08/14/2019 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Completed previously noted requirements. Andy with Canyon builders, Depress landscaped areas as shown on your site and grading plans. Currently the depressed areas are not as wide as indicated. Complete the riprap shown. Provide a hard surface for short term bicycle parking areas. |
07/03/2019 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Complete the work shown on plan. |
07/01/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Trash enclosure pre-grout OK. |
06/20/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Andy 312-1663. Contractor is performing final grading preparing for asphalt. |
04/16/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by CBELL1 - The contractor is grading the site and working on curbs and sidewalks within the right of way. No one on site at this time, 3 PM |
04/09/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by CBELL1 - Contractor is working on drive and sidewalk in the right of way and is also working on grading and trashing closure |