Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - DP16-0241
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/19/2019 | ENGR Engineering Final | BBENEDON | Approved | Entered by DMERANZ1 - Received certification letter from Richard Macias, with Cypress civil development, stating that the site improvements are in substantial conformance to the approved improvement plans. |
08/14/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Completed previously noted requirements. Andy with Canyon builders, Depress landscaped areas as shown on your site and grading plans. Currently the depressed areas are not as wide as indicated. Complete the riprap shown. Provide a hard surface for short term bicycle parking areas. |
07/03/2019 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Andy Wilson is requesting a temporary C of O for funding. Engineering has no issues preventing a temporary C of O. Provide a letter of certification for final grading. Complete all work shown on your development package permit. Depress all landscaping areas 6 inches below curb and lower than sidewalk scupper invert. Trim all cleanouts, install landscaping, bicycle racks etc. Complete work in the right of way. Re-install accessible sign post footings as shown on plan detail. |
07/01/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Inspection for pre-grout. |
08/20/2019 | ENGR Engineering Final | BBENEDON | Approved | Entered by DMERANZ1 - |
08/19/2019 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Provide the required clearance around the bicycle parking, and complete the masonry at the handrail. |
08/14/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Completed previously noted requirements. Andy with Canyon builders, Depress landscaped areas as shown on your site and grading plans. Currently the depressed areas are not as wide as indicated. Complete the riprap shown. Provide a hard surface for short term bicycle parking areas. |
07/03/2019 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Andy Wilson is requesting a temporary C of O for funding. Engineering has no issues preventing a temporary C of O. Provide a letter of certification for final grading. Complete all work shown on your development package permit. Depress all landscaping areas 6 inches below curb and lower than sidewalk scupper invert. Trim all cleanouts, install landscaping, bicycle racks etc. Complete work in the right of way. Re-install accessible sign post footings as shown on plan detail. |