Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - DP16-0228
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/18/2017 | ENGR Engineering Final | DROBERTS | Approved | Entered by DROBERT5 - |
02/17/2017 | ENGR Engineering Final | MRUSSO | Continued | Entered by DROBERT5 - COMPLETE ALL SITE WORK AND OVERHEAD BLDG WORK AND CALL FOR RE-INSPECTION |
06/02/2017 | ENGR Engineering Final | DROBERTS | Approved | Entered by DROBERT5 - |
05/19/2017 | ENGR Engineering Final | DROBERTS | Continued | Entered by DROBERT5 - MET THE CONTRACTOR AND DANNY FROM THE CITY OF TUCSON TRANSPORTATION TO LOOK OVER THE DRIVEWAY APRONS AND SIDEWALKS ON THE NORTHSIDE ENTRANCE. WE THEN LOOKED AT THE ENTRANCE OFF OF ORACLE AND HAVE DETERMINED THAT DANNY WILL CHECK WITH THEIR EOR AND MAKE A DETERMINATION HOW THAT ONE WILL BE POURED. THE NORTHERN DRIVEWAY WILL BE POURED ON MONDAY OR TUESDAY OF NEXT WEEK. |
05/18/2017 | ENGR Engineering Final | DROBERTS | Continued | Entered by DROBERT5 - COMPLETE THE SITE AS SHOWN ON THE APPROVED PLANS, THIS WILL INCLUDE THE NEW WHEEL CHAIR ACCESS RAMP INTO THE RIGHT OF WAY AT THE NORTHWEST CORNER OF THIS SITE. |
12/28/2016 | ENGR Engineering Final | MRUSSO | Continued | Entered by DROBERT5 - ENSURE THE BLDG PERMIT HAS BEEN APPROVED |