Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 06/23/2017 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 06/23/2017 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 06/23/2017 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 01/09/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) CONTRACTOR INSTALLED A "V" DITCH AROUND AREAS SHOWN ON APPROVED PLANS.
2) SILT SOCK WAS INSTALLED ALONG PERIMETER WHERE DRAINAGE HAS OCCURED.
3) MAINTAIN SEDIMENT CONTROLS THROUGHOUT CONSTRUCTION |
| 07/19/2017 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 06/29/2017 |
ENGR Grading Final |
DROBERTS |
Not ready for Inspection |
Entered by DROBERT5 - MET WITH MIKE WILHITE FROM MW MORRISEY AND LOOKED AT THE SLOPES OF THE ADA PARKING SPOT FOR THIS SITE. MIKE RUSSO HAS ALREADY ADVISED THE CONTRACTOR THAT THE SPACES AND ACCESS AISLES ARE OVER THE MAXIMUM FOR THE RUNNING SLOPE AND WILL NEED TO BE REPAIRED BEFORE WE WILL CONSIDER A TCO FOR OCCUPANCY. I VERIFIED TODAY THAT THE RUNNING SLOPE VARIES FROM 2.3% TO 2.8% AT VARIOUS LOCATIONS AND WILL HAVE TO BE REPAIRED TO 2% OR LESS INA ALL DIRECTIONS. |
| 06/21/2017 |
ENGR Grading Final |
DROBERTS |
Not ready for Inspection |
Entered by DROBERT5 - THIS SITE HAS THE SITE WORK TO BE COMPLETED BEFORE IT IS READY FOR A TCO. MIKE WILHITE WILL TRY TO HAVE THIS SITE WORK COMPLETED BEFORE FRIDAY, BUT MAY NEED TO WORK DURING THE WEEKEND. LANDSCAPING INSTALLATION, D.G. PLACEMENT, LOWERING OF THE GREASE INTECEPTOR, HANDRAIL CONSTRUCTION FOR THE PATIO, ARE JUST A FEW OF THE ITEMS THAT ARE MISSING AT THIS TIME. |
| 06/23/2017 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 03/29/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO SITE/GRADING CONCERNS AT THIS TIME |
| 03/17/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT SITE WORK AT THIS TIME, CONTRACTOR INSTALLING UTILITIES AND EXCAVATING BLDG PADS |
| 03/14/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO SITE WORK AT THIS TIME |
| 01/18/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - TOOK PICTURES OF FORMS FOR TWO CATCH BASINS ALONG PARKING LOT. RE-BAR LAY OUT AND FORMS PER APPROVED PLAN - OK TO POUR CONCRETE. |
| 01/13/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - LOOKED AT FORMS AND RE-BAR FOR FLOORS OF TWO STORM WATER CATCH BASINS - OK TO POUR CONCRETE |
| 01/12/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) 30" SRP INSTALLED ALONG NORTH SIDE OF SITE IN PARKING LOT. STORM PIPE INSTALLED PER APPROVED PLAN
2) PICTURES TAKEN OF TRANSITION/CONECTION FROM EXISTING SRP TO NEW SRP - OK TO COVER
3) CONTRACTOR FORMING TWO CATCH BASINS ALONG NEW SRP PER APPROVED PLANS. |
| 01/11/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - CONTRACTOR OVER-EXCAV THE BLDG PAD, NO SITE WORK AT THIS TIME |