Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/03/2020 | ENGR Grading Final | BBENEDON | Approved | Entered by RSALDAT1 - |
06/03/2020 | ENGR Grading Final | BBENEDON | Approved | Entered by RSALDAT1 - |
04/23/2020 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - THIS SITE NEEDS TO BE CHECKED AND INSPECTED TO DETERMINE IF IT IS READY TO BE CLOSED. |
06/03/2020 | ENGR Grading Final | BBENEDON | Approved | Entered by RSALDAT1 - |
05/18/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued.Contractor has completed paving in right of way locations. |
05/08/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Contractor has installed asphalt and is installing interior fencing and canopies |
03/19/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by SFLORES2 - AB installed, ready for asphalt. |
01/23/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - A five design and construction Carlos is bringing dirt onto the site, he’s getting ready to start a new building and large dry well. |
12/19/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by SFLORES2 - Contractor installing site utilities |
09/30/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Installing curbs. I informed Carlos that the sidewalks along Benson highway are within the right of way and require a separate permit and inspection from transportation. |
09/04/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Met with Carlos on site. Contractor is installing block perimeter wall at detention Basin Location, preparing to excavate for the site sewer and installing building wall panels. |
08/15/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Have site perimeter fencing inspected By building Provide drainage openings as specified. |
06/09/2020 | ENGR Grading Final | BBENEDON | Approved | Entered by RSALDAT1 - |
09/05/2019 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Masonry wall at detention basin, as shown, first lift, ok |
08/20/2019 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Footing for site perimeter block wall needs to be inspected by the building inspector as there is no detail for this footing on the development package plan. Note, provisions have been made in the layout to allow for the drainage openings required. |