Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Complete (Recurring)
Inspection History: ENGR Engineering Final
Permit Number - DP16-0112
Inspection Description - ENGR Engineering Final
Inspection Status - Complete (Recurring)
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/23/2020 | ENGR Engineering Final | RLEDONNE | Continued | Entered by RSALDAT1 - Continued. Material and debris stock piles remain on site. There is no current activity on site. Tumbleweeds have begun to grow throughout the site. |
12/04/2018 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by CBELL1 - Correct breach at basin. Cap broken sewer risers. Remove stock piles as noted by Dave Roberts on October 15th 2018. Stabilized Lots as noted for rdld on May 8th 2018. Met with Jim on site 310 9245 |
10/15/2018 | ENGR Engineering Final | DROBERTS | Continued | Entered by DROBERT5 - THESE INSPECTIONS CAN NOT BE FINALED TILL ALL THE WORK HAS BEEN COMPLETED ON THIS SITE AS SHOWN ON THE APPROVED PLANS. |
10/15/2018 | ENGR Engineering Final | DROBERTS | Approved | Entered by DROBERT5 - |
05/30/2018 | ENGR Engineering Final | RLEDONNE | Continued | Entered by RLEDONN1 - LANDSCAPING ON EAST SIDE OF SITE. |
05/24/2018 | ENGR Engineering Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
03/09/2018 | ENGR Engineering Final | RLEDONNE | Continued | Entered by RLEDONN1 - TRANFER PIPIS INSTALLED FROM NEW BASIN INTO BASIN ON WEST SIDE OF CAR WASH AND WORKING ON RIP-RAP. |
08/18/2017 | ENGR Engineering Final | DROBERTS | Denied | Entered by DROBERT5 - NO ONE ONSITE FOR THIS INSPECTION |