Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - DP16-0111
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/21/2019 | ENGR Engineering Final | BBENEDON | Approved | Entered by CBELL1 - |
03/19/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by CBELL1 - |
12/05/2018 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by CBELL1 - Superintendent does not have a permit card. |
03/21/2019 | ENGR Engineering Final | BBENEDON | Approved | Entered by CBELL1 - this is the final phase of this project on the north east site. The rest of the site was inspected and completed previously by other inspector |
03/19/2019 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by CBELL1 - ADA parking spaces for this phase in the north east corner of the site are In compliance |
03/29/2018 | ENGR Engineering Final | MRUSSO | Continued | Entered by DROBERT5 - 1) COMPLETE SITE/GRADING WORK PER YOUR APPROVED PLANS. 2) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD. 3) HC PARKING ALONG THE NORTH SIDE OF BLDG DOES NOT MEET THE NO GREATER THAN 2% SLOPE IN ANY DIRECTION REQUIREMENT. |