Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 04/10/2019 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by CBELL1 - |
| 12/03/2018 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by CBELL1 - Galvanized pipe installed into drainage canal. Need to see approved plans. |
| 06/08/2018 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by DROBERT5 - LOOKED AT THE SIDEWALK AND THE HANDICAP PARKING LOCATIUONS ON THIS SITE FOR COMPLIANCE. MOST OF THE AREAS APPEAR TO BE COMPLIANT, OTHER AREAS WILL BE CHECKED AGAIN AT A LATER DATE ONCE ALL OF THE CONSTRUCTION MATERIAL AND VEHICLES HAVE BEEN REMOVED. |
| 04/27/2018 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - SITE PROGRESS INSPECTION - NO SIGNIFICANT SITE, GRADING, LANDSCAPING CONCERNS AT THIS TIME |
| 04/27/2018 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 03/12/2018 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) CONTRACTOR REVISED PLANS TO SHOW CHANGES MADE TO LOADING RAMP
2) ADDITION OF CATCH BASIN AND 12" PVC STORM PIPE.
3) PVC AND CLEAN OUT INSTALLED PER PLAN - OK TO COVER
CALL FOR INSPECTION PRIOR TO COVERING CATCH BASIN |
| 03/09/2018 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO CONTACT ON SITE |
| 03/02/2018 |
ENGR Grading Final |
MRUSSO |
Correction Required |
Entered by DROBERT5 - 1) CHANGES MADE TO STORM WATER DRAINAGE ON SITE
2) PROVIDE AN APPROVED PLAN SHOWING CHANGES THAT WERE MADE FOR INSPECTION, OR CONSTRUCT THE SITE PER THE ORIGINAL APPROVED SITE/GRADING PLAN.
3) PROVIDE COPIES OF YOUR STORM WATER MAINT SELF INSPECTIONS PER YOUR SWPPP.
4) CALL FOR INSPECTION PRIOR TO COVERING STORM PIPE INSTALLED ALONG THE NW SIDE OF SITE. |
| 12/18/2018 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by CBELL1 - |
| 12/18/2018 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by CBELL1 - |
| 03/02/2018 |
ENGR Grading Final |
MRUSSO |
Correction Required |
Entered by DROBERT5 - 1) CHANGES MADE TO STORM WATER DRAINAGE ON SITE
2) PROVIDE AN APPROVED PLAN SHOWING CHANGES THAT WERE MADE FOR INSPECTION, OR CONSTRUCT THE SITE PER THE ORIGINAL APPROVED SITE/GRADING PLAN.
3) PROVIDE COPIES OF YOUR STORM WATER MAINT SELF INSPECTIONS PER YOUR SWPPP.
4) CALL FOR INSPECTION PRIOR TO COVERING STORM PIPE INSTALLED ALONG THE NW SIDE OF SITE. |
| 12/26/2018 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by CBELL1 - |