Permit: DP16-0108

Parcel: 11619153A


Addresses:

450 N FREEWAY

Inspection Status: Passed

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
04/10/2019 ENGR Grading Final DROBERTS Approved Entered by CBELL1 -
12/03/2018 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - Galvanized pipe installed into drainage canal. Need to see approved plans.
06/08/2018 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - LOOKED AT THE SIDEWALK AND THE HANDICAP PARKING LOCATIUONS ON THIS SITE FOR COMPLIANCE. MOST OF THE AREAS APPEAR TO BE COMPLIANT, OTHER AREAS WILL BE CHECKED AGAIN AT A LATER DATE ONCE ALL OF THE CONSTRUCTION MATERIAL AND VEHICLES HAVE BEEN REMOVED.
04/27/2018 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - SITE PROGRESS INSPECTION - NO SIGNIFICANT SITE, GRADING, LANDSCAPING CONCERNS AT THIS TIME
04/27/2018 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
03/12/2018 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) CONTRACTOR REVISED PLANS TO SHOW CHANGES MADE TO LOADING RAMP 2) ADDITION OF CATCH BASIN AND 12" PVC STORM PIPE. 3) PVC AND CLEAN OUT INSTALLED PER PLAN - OK TO COVER CALL FOR INSPECTION PRIOR TO COVERING CATCH BASIN
03/09/2018 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO CONTACT ON SITE
03/02/2018 ENGR Grading Final MRUSSO Correction Required Entered by DROBERT5 - 1) CHANGES MADE TO STORM WATER DRAINAGE ON SITE 2) PROVIDE AN APPROVED PLAN SHOWING CHANGES THAT WERE MADE FOR INSPECTION, OR CONSTRUCT THE SITE PER THE ORIGINAL APPROVED SITE/GRADING PLAN. 3) PROVIDE COPIES OF YOUR STORM WATER MAINT SELF INSPECTIONS PER YOUR SWPPP. 4) CALL FOR INSPECTION PRIOR TO COVERING STORM PIPE INSTALLED ALONG THE NW SIDE OF SITE.
12/18/2018 ENGR Grading Final BBENEDON Approved Entered by CBELL1 -
12/18/2018 ENGR Grading Final BBENEDON Approved Entered by CBELL1 -
03/02/2018 ENGR Grading Final MRUSSO Correction Required Entered by DROBERT5 - 1) CHANGES MADE TO STORM WATER DRAINAGE ON SITE 2) PROVIDE AN APPROVED PLAN SHOWING CHANGES THAT WERE MADE FOR INSPECTION, OR CONSTRUCT THE SITE PER THE ORIGINAL APPROVED SITE/GRADING PLAN. 3) PROVIDE COPIES OF YOUR STORM WATER MAINT SELF INSPECTIONS PER YOUR SWPPP. 4) CALL FOR INSPECTION PRIOR TO COVERING STORM PIPE INSTALLED ALONG THE NW SIDE OF SITE.
12/26/2018 ENGR Grading Final BBENEDON Approved Entered by CBELL1 -