Permit: DP16-0108

Parcel: 11619153A


Addresses:

450 N FREEWAY

Inspection Status: Passed

Inspection History: SITE - Stormwater Follow-up

Date Description Inspector Results Comments
04/10/2019 SITE - Stormwater Follow-up DROBERTS Approved Entered by CBELL1 -
09/05/2018 SITE - Stormwater Follow-up DROBERTS Partial Approval Entered by DROBERT5 - NO CONCERNS AT THIS TIME, STILL WAITING FOR THE APPROVED REVISED DRAWINGS THAT WILL BE UTILIZED TO COMPLETE THE SITE DRAINAGE.
07/13/2018 SITE - Stormwater Follow-up GWEST Continued Entered by DROBERT5 - CONTACTED ZACH W/CANYON AND METE WITH HIM ON SITE TO DISCUSS WHAT ARE THE CURRENT STATUS FOR THIS SITE. HE ADVISED ME THAT THEY ARE STILL WAITING FOR THE DRAWINGS FOR THE MODIFICATIONS THAT ARE NEEDED AT THE NORTHWEST CORNER OF THIS SITE. THE WORK ON THE SITE IS ALMOST COMPLETE EXCEPT FOR THE CHANGES THAT ARE GOING TO BE PROPOSED. I ALSO ADVISED HIM THAT TRANSPORTATION HAS SOME CONCERNS IN REGARDS TO THE TRANSFORMER THAT IS TO BE INSTALLED AT A LATER. ELIZABETH LEIBOLD WANTS TO BE ADVISED THAT THIS IS NOT WITHIN THE AREA OF THE EROSION HAZARD SETBACK AT THE NORTHEAST CORNER OF THIS SITE.
06/08/2018 SITE - Stormwater Follow-up DROBERTS Continued Entered by DROBERT5 - THIS INSPECTION HAD BEEN FINALED BY MIKE RUSSO BUT THE SITE IS NBOT COMPLETE AT THIS TIME AND WILL BE REOPENNED
04/27/2018 SITE - Stormwater Follow-up MRUSSO Approved Entered by DROBERT5 -
03/02/2018 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) CHANGES MADE TO STORM WATER DRAINAGE ON SITE 2) PROVIDE AN APPROVED PLAN SHOWING CHANGES THAT WERE MADE FOR INSPECTION, OR CONSTRUCT THE SITE PER THE ORIGINAL APPROVED SITE/GRADING PLAN. 3) PROVIDE COPIES OF YOUR STORM WATER MAINT SELF INSPECTIONS PER YOUR SWPPP. 4) CALL FOR INSPECTION PRIOR TO COVERING STORM PIPE INSTALLED ALONG THE NW SIDE OF SITE.