Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: PDSD Site/Engineering Division - Landscaping
Permit Number - DP16-0046
Inspection Description - PDSD Site/Engineering Division - Landscaping
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/21/2017 | PDSD Site/Engineering Division - Landscaping | DROBERTS | Approved | Entered by DROBERT5 - |
04/14/2017 | PDSD Site/Engineering Division - Landscaping | RLEDONNE | Continued | Entered by RLEDONN1 - INSTALL RIP-RAP PER AP PLANS. |
04/21/2017 | PDSD Site/Engineering Division - Landscaping | DROBERTS | Approved | Entered by DROBERT5 - |
04/14/2017 | PDSD Site/Engineering Division - Landscaping | DROBERTS | Correction Required | Entered by DROBERT5 - I CONTACTED JOSEPH LINVILLE AND WE DISCUSSED THE CHANGES THAT HAVE BEEN MADE IN THE FIELD.WE WILL ACCEPT MINOR MOVEMENT OF PLANTS IN A GENERAL AREA. WE WILL NOT ACCEPT WITHOUT DRAWINGS ANY CHANGES THAT HAVE REMOVED PLANTS OR TREES FROM ONE AREA AND HAVE BEEN PLACED IN ANOTHER AREA. I WILL BE ASKING THE CONTRACTOR TO HAVE THE REVISED DRAWINS REVIEWED AND APPROVED BEFORE WE ACCEPT THE WORK IN THE FIELD. ALL OTHER WORK IN THE FIELD THAT MATCHES THE APPROVED PLANS CAN BE ACCEPTED AT THIS TIME. |
04/14/2017 | PDSD Site/Engineering Division - Landscaping | DROBERTS | Correction Required | Entered by DROBERT5 - SITE HAS BEEN CHECKED AND CHANGES HAVE BEEN MADE TO THE SITE, BUT THERE IS NO REVISED DRAWINGS FOR THE CHANGES. I ASKED THE CONTRACTOR TO HAVE THE CONTRACTOR SUBMIT THE CHANGES TO JOSEPH LINVILLE SO THAT THIS SITE CAN BE INSPECTED LATER WITH A SET OF REVISED DRAWINGS. HE ADVISED ME THAT THE EOR HAS ALREADY HAD THE CHANGES APPROVED BY JOSEPH AND IT WILL BE HANDLED AS A TIER 1 REVIEW WHERE THE FIELD INSPECTOR CAN ACCEPT THE CHANGES WITHOUT A REVISED DRAWING. |
04/19/2017 | PDSD Site/Engineering Division - Landscaping | DROBERTS | Partial Approval | Entered by DROBERT5 - CHANGES HAVE BEEN MADE TO THIS SITE IN THE EASTERN PARKING LOTS. TREES HAVE BEEN REMOVED FROM THE ENTRANCES AND HAVE BEEN PLACED IN OTHER LOCATIONS ON THE SITE. I HAVE ASKED THE CONTRACTOR TO CONTACT THE ENGINEER OF RECORD AND HAVE THESE CHANGES SUBMITTED FOR APPROVAL. |
04/18/2017 | PDSD Site/Engineering Division - Landscaping | DROBERTS | Partial Approval | Entered by DROBERT5 - MINOR CHANGES HAVE BEEN MADE IN THE PARKING LOTS ON THE EAST SIDE OF THE SITE, THESE NEED TO NOTED ON REVISED DRAWINGS FOR THIS SITE. |