Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 03/05/2021 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by KROBLES1 - Continued. Inspector recommends closing permit. Engineering final was approved June 2019. All work has been completed. |
| 03/05/2021 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by KROBLES1 - Continued. Inspector recommends closing permit. Engineering final was approved June 2019. All work has been completed. |
| 02/18/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Inspector recommends closing permit. Engineering final was approved June 2019. All work has been completed. |
| 06/10/2019 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by CBELL1 - |
| 03/06/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by CBELL1 - The contractor is installing a double trash enclosure. |
| 03/12/2019 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by CBELL1 - Trashing closure |
| 03/06/2019 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by CBELL1 - Trash enclosure footing is OK for concrete. Recall inspection for pre-grout, bollard installation and pre-slab inspection. |
| 06/10/2019 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by CBELL1 - |
| 04/03/2019 |
ENGR Grading Final |
DROBERTS |
Not ready for Inspection |
Entered by CBELL1 - inspection will be rescheduled for tomorrow morning |
| 03/12/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by CBELL1 - Trash enclosure is OK for grout |
| 03/06/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by CBELL1 - The parking lot in the rear of the building has already been poured in concrete, the accessible space and loading zone appear to be existing. |