Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP16-0008

Parcel: 117144880


Addresses:

19 W 17TH ST


Inspection Status: Complete (Recurring)

Inspection History: SITE - Stormwater Follow-up

Permit Number - DP16-0008

Inspection Description - SITE - Stormwater Follow-up

Inspection Status - Complete (Recurring)

Date Description Inspector Results Comments
05/04/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 -
02/08/2019 SITE - Stormwater Follow-up BBENEDON Continued Entered by CBELL1 - No issues visible from the entrance gate. Jobsite locked.
12/21/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by CBELL1 - Walk site with GC when over Basin at North End of site call Dave back in on Wednesday the 26th.
10/17/2018 SITE - Stormwater Follow-up DROBERTS Continued Entered by DROBERT5 - NO CONCERNS AT THIS TIME, SITE STAYING CLEAN.
08/14/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO TREACK OUT AT THIS TIME.
07/26/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
06/19/2018 SITE - Stormwater Follow-up DROBERTS Correction Required Entered by DROBERT5 - THE SITE NEEDS TO BE MONITORED BY THE CONTRACTOR TO ENSURE THAT THEY ARE NOT VIOLATING THE STORMWATER ORDINANCE. CURRENTLY THEY HAVE BEEN DEPOSITING CONCRETE THROUGHOUT THE SITE WHEN THEY HAVE COMPLETED THE PALCEMENT. I HAVE DIRECTED THEM TO MAKE SURE THAT ALL OF THE CONCRETE IS CLEANED UP AT THIS AND TO MAKE SURE THAT THERE IS NO VIOLATIONS LIKE THIS IN THE FUTURE.
06/15/2018 SITE - Stormwater Follow-up DROBERTS Continued Entered by DROBERT5 - DROVE THROUGH THE SITE AND FIND NO CONCERNS AT THIS TIME. I WILL INSPECT THE SITE EARLY NEXT WEEK TO MAKE SURE THAT IT IS READY FOR THE MONSOON RAINS THIS SEASON.
05/14/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - REPAIRS HAVE BEEN MADE.
05/07/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET WITH GC ABOUT REPAIRS TO SWPPP CONTROLS.
04/18/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS.
04/11/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
03/15/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS.
03/12/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS.
02/20/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
02/12/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET WITH GC ABOUT PROVIDING A WASH OUT AND WENT OVER BASIN.
02/01/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - REPAIRS HAVE BEEN MADE TO SWPPP.
01/30/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET WITH GC ABOUT SWPPP REPAIRS THAT STILL HAVE NOT BEEN DONE.
01/24/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET ON SITE WITH GC ABOUT SWPPP REPAIRS.
01/08/2018 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS.
12/28/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
12/14/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET WITH GC ABOUT SWPPP REPAIRS.
11/21/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME
11/15/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
10/27/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
10/24/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - no concerns at this time.
10/16/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
10/11/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
09/22/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
09/19/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET WITH NEW SUPER ON SITE WENT OVER SWPPP CONTROLS.
08/14/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO TRACK OUT.
08/07/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - SWPPP CONTROLS HAVE BEEN ADDED AT NORTH WEST END OF SITE.
07/25/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET WITH GC ON SITE NEEDS REPAIRS TO SWPPP CONTROLS ON WEST SIDE OF SITE.
04/26/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by DROBERT5 - NO CONCERNS AT THIS TIME.
03/06/2017 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.