Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 05/04/2017 |
ENGR Engineering Final
|
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 04/27/2017 |
ENGR Engineering Final
|
MRUSSO |
Partial Approval |
Entered by DROBERT5 - PARTIAL APPROVAL - FINAL NOT TO BE GIVEN UNTIL THE ITEMS BELOW ARE COMPLETED:
1) APPROVE THE FINAL GRADING INSPECTION FOR DP15-0194
2) PROVIDE A FINAL REVISED APPROVED PLAN FOR FINAL INSPECTION
3) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD |
| 05/04/2017 |
ENGR Engineering Final
|
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 04/27/2017 |
ENGR Engineering Final
|
MRUSSO |
Partial Approval |
Entered by DROBERT5 - PARTIAL APPROVAL - FINAL NOT TO BE GIVEN UNTIL THE ITEMS BELOW ARE COMPLETED:
1) APPROVE THE FINAL GRADING INSPECTION FOR DP15-0194
2) PROVIDE A FINAL REVISED APPROVED PLAN FOR FINAL INSPECTION
3) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD |
| 01/04/2017 |
ENGR Engineering Final
|
DROBERTS |
Not ready for Inspection |
Entered by DROBERT5 - THE CONTRACTOR SCHEDULED THE WRONG INSPECTION, HE NEEDED TO SCHEDULE THE FOOTER INSPECTION FOR THE PERIMETER WALL. THIS WORK WAS INSPECTED BY BRUCE STEVENS TODAY. |