Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP15-0126
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/09/2017 | ENGR Grading Final | RLEDONNE | Approved | Entered by RLEDONN1 - |
10/14/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - MET WITH GC ABOUT PARKING OFF SITE . |
01/09/2017 | ENGR Grading Final | RLEDONNE | Approved | Entered by RLEDONN1 - |
11/21/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - WORKING ON BASINS. |
09/30/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - MET WITH GC ABOUT BOLLARDS ON NORTH SIDE OF BUILDING. |
09/21/2016 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - LOOKED OVER THE ROCK RIP PLACEMENT IN THE DRAINAGE WAYS OF THIS SITE. EVERYTHING IS LOOKING OK IN REGUARDS TO THE PLACEMENT AND THE DEPTHS. I HAVE ASKED TO CONTRACTOR TOO EITHER BURY THE FABRIC IN A TOE DOWN TRENCH, OR PLACE ADDITIONAL MATERIAL ON THE OUTER AREAS ON THE INLETS SIDES TO PREVENT THE UNDERMINING OF THE FABRICK. |
08/29/2016 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - CHECKED THE REBAR IN THE RETAINING WALL FOOTER ALONG THE SOUTHSIDE OF THE CHANNEL LOCATED AT THE NORTHEAST CORNER OF THIS SITE. THE CREW HAS BEEN CLEARED FOR THE POURING OF THE FOOTER |
08/29/2016 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - MET WITH THE CONTRACTOR AND LOOKED AT THE FOLLOWING ITEMS FOR GROUT: 10 THE CMU WALL SOUTH OF THE FUTURE ROADWAY ALONG THE SOUTH SIDE OF THE PROJECT, LOCATED WEST OF THE CONSATRUCTION TRAILOR FOR APPROXIMATELY 100 FEET. 2) THE CMU WALLS FOR THE TRASH ENCLOSURE. BOTH OF THESE AREAS HAVE BEEN APPROVED FOR THE 1ST 4 FOOT LIFT OF THE WALLS. ALSO LOOKED AT THE STEEL FOR THE RETAINING WALL ALONG THE NORTHSIDE OF THE PROJECT SOUTH OF THE DRAINAGE CHANNEL BETWEEN INDIAN AGENCY ROAD AND THE EAST DRIVEWAY OFF OF VALENCIA, THIS AREA WILL BE POURED LATER TODAY. |
07/20/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - MET WITH THE TWO GC'S ABOUT FOOTERS FOR EAST SIDE OF NEW SMALL BUILDING. |
06/30/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - LOOKED AT STORM DRAIN TIE IN ON SOUTH SIDE OF BUILDING. |
06/24/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - STORMWATER PIPING PER HIGH LIGHT ON PLANS . REBAR FOR WING WALLS FOR BOX CULVERS ON SOUTH EAST SIDE. |
06/22/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - OK TO GROUT NORTH EAST RETAINING WALL. AND INSTALLING 18' OF 24'' HDPE. STROM DRAIN PIPING ON SOUTH SIDE OF BUILDING. |
06/17/2016 | ENGR Grading Final | RLEDONNE | Partial Approval | Entered by RLEDONN1 - RETAINING WALL REBAR OK TO GROUT ON SOUTH EAST SIDE OF SITE. |
04/22/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - RETAINING WALLS ON EAST SIDE OF SITE REBAR INSTALLED. |
04/19/2016 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - CHECKED THE REBAR THIS MORNING TO ENSURE THAT IT IS COMPLETE AND READY FOR TODAYS POUR. THE WING WALLS FOR THIS STRUCTURE WILL BE POURED AT A LATER DATE. |
04/18/2016 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - CREWS PLACING REBAR IN THE TOP MAT OF THE ROOF SECTION. THIS WILL BE POURED TOMORROW. I WILL RECHECK THE REBAR IN THE MORNING ONCE IT HAS BEEN COMPLETELY TIED. |
04/14/2016 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - THE FOLLOWING ITEMS ARE BEING WORKED ON AT THIS TIME: 1) FORMING WALLS ON THE NORTHEN MOST BOX CULVERT OFF OF INDIAN AGENCY ROAD. THIS WILL BE POURDED EITHER LATER THIS WEEK OR NEXT WEEK. 2) THE PIPE CREWS ARE WORKING ON THE INSTALLATION OF THE MAIN WATERLINE ON THE NORTHSIDE OF THE FRYS FROM THE WEST TO THE EAST. |
04/11/2016 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - 1) CREWS WORKING ON THE POURING OF CONCRETE FOR THE NORTHERN BOX CULVERT ON INDIAN AGENCY ROAD. 2) CREW WORKING ON INSTALLING THE WATER LINE AT THE NORTH WEST CORNER OF THE SITE BEHIND BIG O TIRE, THIS WORK IS BEING INSPECTED BY THE WATER DEPARTMENT. |
03/31/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - WORKING ON HDPE PIPING TO THE NORTH OF NORTH EAST BASIN. |
03/29/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - WORKING ON BASINS. |
03/24/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - BACK FILLING AT SOUTH BASIN AND INSTALLING 6'' OF ROCK ON TOP AT NORTH EAST BASIN. |
03/21/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - WORKING ON BASINS. |
03/18/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - STILL WORKING ON EAST BASINS. |
03/17/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSTALLING ROCK OVER PIPING IN SOUTH BASIN. |
03/16/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - STILL INSTALLING CHAMBERS. |
03/15/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSTALLING CHAMBERS OVER 6'' OF ROCK AND FABRIC IN BASINS. |
03/14/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - |
03/08/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - GRAVEL ON SITE FOR RETENTION BASIN. AND WORKING ON FINAL GRADING. |
02/09/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - MET WITH GC TRUCKING IN FILL ON SITE STREETS LOOK GOOD AT THIS TIME. |
07/18/2017 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
10/06/2016 | ENGR Grading Final | RLEDONNE | Approved | Entered by RLEDONN1 - |
08/29/2016 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by DROBERT5 - MET WITH THE CONTRACTOR AND LOOKED AT THE FOLLOWING ITEMS FOR GROUT: 10 THE CMU WALL SOUTH OF THE FUTURE ROADWAY ALONG THE SOUTH SIDE OF THE PROJECT, LOCATED WEST OF THE CONSATRUCTION TRAILOR FOR APPROXIMATELY 100 FEET. 2) THE CMU WALLS FOR THE TRASH ENCLOSURE. BOTH OF THESE AREAS HAVE BEEN APPROVED FOR THE 1ST 4 FOOT LIFT OF THE WALLS. ALSO LOOKED AT THE STEEL FOR THE RETAINING WALL ALONG THE NORTHSIDE OF THE PROJECT SOUTH OF THE DRAINAGE CHANNEL BETWEEN INDIAN AGENCY ROAD AND THE EAST DRIVEWAY OFF OF VALENCIA, THIS AREA WILL BE POURED LATER TODAY. |
06/20/2016 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by DROBERT5 - CREWS ARE WORKING ON THE PLACEMENT OF REBAR FOR THE WALLS AND ROOF OF BOX CULVERT #1, IT IS APPROVED AT THIS TIME FOR THE PLACEMENT OF CONCRETE, THIS IS EXPECTED TO BE POURED TOMORROW MORNING. |
05/20/2016 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by DROBERT5 - LOOKED OVER THE SITE TO SEE WHAT WORK IS HAPPENING AT THIS TIME. THE CREWS ARE CURRENTLY WORKING ON THE INSTALLATION OF THE REBAR FOR COR THE FOOTERS FOR THE CULVERTS #1 & #2 SOUTH VALENCIA FOR THE ROADWAYS INTO THE SITE. THEY ARE REMOVING ALL OF THE LOOSE MATERIAL FROM WITHIN THE FOOTER AREAS AND WILL BE READY FOR THE PLACEMENT OF CONCRETE LATER ON THIS MORNING. |
06/14/2016 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by DROBERT5 - THE CREW IS TIEING THE STEEL FOR THE FOOTES AND THE FLOOR SLAB OF BOX CULVERT #1, THIS APPROVED AT THIS TIME FOR THE POURING OF THE CONCRETE. |