Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 08/02/2017 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 08/02/2017 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 03/29/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO SITE/GRADING CONCERNS AT THIS TIME |
| 08/02/2017 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 06/06/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) CONTRACTOR INSTALLING STORM PIPE ALONG WEST SIDE.
2) PIPE INSTALLED PER APPROVED PLAN, OK TO COVER, PICTURES TAKEN.
3) NO STORM WATER CONCERNS |
| 05/03/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) INSTALL OF 4-12" CMP ALONG WEST ENTRANCE TO SITE.
CHANGE FROM 2-18" CMP TO 4-12" CMP.
2) PROVIDE AN COT APPROVED PLAN FOR FINAL INSPECTION SHOWING ALL CHANGES MADE TO THE SITE.
3) PIPE WAS INSTALLED PER REVISED PLAN - OK TO COVER |
| 02/24/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) LOOKED AT 24" CMP ALONG S./SW SIDE OF SITE - PCS TAKEN.
PIPE IN PLACE W/ BEDDING, SLOPE OK
ENSURE PROPER COVER ON PIPE, 1 FOOT MIN.
2) CONTRACTOR FORMING TYPE 4 CATCH BASIN - PICS TAKEN
PROVIDE PICTURES OF FINISHED FORMS
|
| 01/13/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - MINIMAL SITE WORK AT THIS TIME |
| 01/11/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - CALL FOR INSPECTION PRIOR TO COVERING ALL UNDERGROND STORM PIPE |
| 09/09/2016 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by DROBERT5 - CREWS WORKING ON GROUTING OF THE 2ND LIFT OF THE WALLS THAT BELOW THE EXISTING GRADE. |
| 08/02/2017 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 07/07/2017 |
ENGR Grading Final |
MRUSSO |
Partial Approval |
Entered by DROBERT5 - RE-BAR FOR TRASH ENCLOSURE PAD AND APRON INSTALLED PER APPROVED PLANS |
| 06/15/2017 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - RE-BAR LAY OUT AND FOOTING FOR 30" SCREEN WALL ALONG THE WEST SIDE HAVE BEEN CONSTRUCTED PER APPROVED PLANS, OK TO POUR CONCRETE/ PICTURES TAKEN |
| 06/09/2017 |
ENGR Grading Final |
MRUSSO |
Partial Approval |
Entered by DROBERT5 - 1) ENSURE WALL RE-BAR LAY OUT IS #4 @ 18" OC BOTH WAYS.
2) FOOTINGS AND RE-BAR FOR TRASH ENCLOSURE INSTALLED PER APPROVED PLANS PIC TAKEN - OK TO POUR. |