Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
Permit Number - DP15-0102
Inspection Description - ENGR Engineering Final
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | ENGR Engineering Final | Not Ready | ||
| 10/27/2022 | ENGR Engineering Final | Not Ready | ||
| 01/15/2025 | ENGR Engineering Final | Not Ready | Several areas still need to be finished | |
| 04/24/2025 | ENGR Engineering Final | Not Ready | Not ready. 1. Significant trash in common areas throughout. 2. Behind lots 303, slope is not per plans, should be 3:1 away from wall with riprap and Hydroseed. 3. There is no parking lot striping or handicap signs at the park on Tortoise Canyon Lane. 4. 8-cell sidewalk scupper on NE cul-de-sac of Meagan Ridge Place is broken with exposed rebar. 5. Sidewalk panel broken along West side of Rincon Knolls Loop between Huston Canyon and Tortoise Point. 6. C.A. between lots 249 & 250 is unfinished. 7. There is no stabilization on the NE corner of lot 240, there is significant erosion exposing the wall footing. |
|
| 08/01/2025 | ENGR Engineering Final | Not Ready | We still have unfinished lots that will require a final walk to be done. Letter concerning DG in -lace of hydro seed will be submitted as well as revisions for changes observed in drainage areas. 1 basin needs attention now that this area is completed where drainage from 2 cul de sacs run into. |
|
| 08/01/2025 | ENGR Engineering Final | Not Ready | We still have unfinished lots that will require a final walk to be done. Letter concerning DG in -lace of hydro seed will be submitted as well as revisions for changes observed in drainage areas. 1 basin needs attention now that this area is completed where drainage from 2 cul de sacs run into. |
|
| 09/26/2023 | ENGR Engineering Final | Not Ready | not ready yet until further more inspections is needed | |
| 09/26/2023 | ENGR Engineering Final | Not Ready | not ready yet until further more inspections is needed |