Permit: DP15-0065

Parcel: Unknown


Addresses:

3570 N CRAYCROFT RD

Inspection Status: Passed

Inspection History: SITE - Stormwater Follow-up

Date Description Inspector Results Comments
08/16/2016 SITE - Stormwater Follow-up RLEDONNE Approved Entered by RLEDONN1 -
07/06/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
06/17/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET WITH GRADING CONRACTOR ABOUT ADDING SWPPP CONTROLS AT SOUTH WEST SIDE OF SIDE.
05/04/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET WITH GC ABOUT CLEAN UP OF SILT AND REPAIRS TO SWPPP CONTROLS.
04/28/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - CALLED GC ABOUT SWPPP CONTROL REPAIRS.
03/18/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET WITH GC ABOUT ADDING TRACK OUT ROCK.
02/25/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
02/10/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
02/03/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - ROCK HAS NOT BEEN ADDED TO TRACK OUT AT GATE.
01/29/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET WITH GC ABOUT ADDING ROCK AT GATE.
01/28/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - REPAIRS HAVE BEEN DONE.
01/19/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET WITH GC ABOUT REPAIRS TO SWPPP CONTROLS.
01/13/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
01/08/2016 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
12/29/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
12/22/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by DROBERT5 - NO CONCERNS AT THIS TIME.
12/15/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO ACTIVITY ON SITE . DO TO RAIN.
12/14/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - STILL WORKING ON SWPPP COTROLS.
12/11/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - WORKING ON REPAIRING SWPPP CONTROLS.
11/24/2015 SITE - Stormwater Follow-up RLEDONN1 Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. STILL MOVING DIRT.
11/12/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - TRACK OUT ON CRAYCROFT. NO WASHOUT FOR CONCRETE. NEED TO CLEAN AND ADD TRACKOUT ROCK AND REPAIR SWPPP CONTROLS.
11/04/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
10/30/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
10/28/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS ON TRACK OUT.
10/27/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - STREET SWEEPER ON SITE.
10/26/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - WALKED SITE GOT WITH GC REP TO REPAIR CONTROLS .
10/23/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - GRADING ACTIVITY ONLY.
10/20/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - STREET SWEEPER WORKING FROM 10 AM TO 2PM.
10/19/2015 SITE - Stormwater Follow-up RLEDONNE Continued Entered by RLEDONN1 - MET WITH GC ABOUT TRACK OUT ON TO CRAY CROFT AND SWPPP REP FOR GC THEY SAID THAT THE ROAD WOULD BE CLEANED WHEN TRUCKS ARE RUNNING.